Description
Egmond aan Zee Offshore Wind Farm (OWEZ), formerly named the Near Shore Windfarm (NSW), is the first offshore wind farm constructed off the Dutch North Sea and was considered a demonstration project to study the technical, ecological, economic, and social feasibility of offshore wind farms.
OWEZ consists of 36 turbines with a capacity of 3 MW each and was developed as part of the NoordzeeWind joint venture between Shell and Vattenfall. In March 2021, Shell acquired Vattenfall’s share and became the sole owner of the wind farm.
OWEZ was originally planned to operate until 2027. Following a Power Purchase Agreement (PPA) with Google, Shell NoordzeeWind received the necessary permits from the Dutch government to extend the wind farm’s operational life until 2031. This extension allows OWEZ to supply renewable power to the Dutch electricity grid for almost five years longer than initially planned.
Location
The wind farm is located 10-18 km off the coast of Egmond aan Zee, Netherlands in the Dutch North Sea. It lies within the Dutch Exclusive Economic Zone (EEZ), in water depths ranging from approximately 12 to 20 m and covers a total area of about 27 km2.
Project Timeline
- May 2025: Shell received a 5-year extension with corporate Power Purchase Agreement with Google
- March 2021: Shell fully acquired OWEZ from Vattenfall
- October 2007: Full commercial operation
- April 2007: Official inauguration
- December 2006: Construction completed
- June 2005: Construction began
- May 2005: Financial close reached and all contracts signed
- June 2002: Site selection and NoordzeeWind won the competitive tender
- September 1997: Feasibility study completed
Licensing Information
The licensing and permitting processes for OWEZ involved several key stakeholders and Dutch authorities. Rijkswaterstaat (within the Ministry of Infrastructure and Water Management) was responsible for managing the spatial planning and permitting of OWEZ, ensuring the project complied with marine safety, environmental, and water management regulations. Continuon, the local grid operator, arranged the grid connection and managed permits for cable installation and integration into the national electricity network.
Key Environmental Issues
OWEZ was part of a demonstration project aimed at assessing both the technological and environmental challenges of offshore wind development. A Monitoring and Evaluation Program (NSW-MEP) was designed to gather data on the ecological, technical, economic, and social effects of the wind farm from 2006 to 2012. Studies were conducted to evaluate impacts on flying birds, including on their flight paths, altitudes, and flux, as well as the effects on seabirds and non-marine migrating birds. Additional studies focused on impacts on harbour porpoises, using static acoustic monitoring before and after the construction of the wind farm. During construction, Horizontal Directional Drilling (HDD) was used for cable landfall beneath sensitive coastal dunes. As a relatively new technique at the time, HDD helped minimize environmental disturbance compared to traditional methods and is now standard practice in offshore wind projects in the region.
The Monitoring and Research Programme 2017-2021 (Wozep 2016) describes the overall monitoring and research programme for the Dutch Offshore Wind Ecological Programme (Wozep).