Skip to main content

Partnering with WREN, questionnaires are sent to offshore wind energy developers around the world who are involved in environmental monitoring. This page provides contextual project information and highlights environmental monitoring, providing links to available data and reports. Content is updated annually.

Horns Rev 3

Description

The Horns Rev 3 Offshore Wind Farm consists of 49 wind turbines with a power output of 8.3 MW each, resulting in a total power output of approximately 400 MW. Horns Rev 3 was Denmark’s largest offshore wind farm at the time of construction, is capable of powering around 425,000 households, and will provide some of the cheapest offshore wind electricity in Europe. Vattenfall won the right to construct Horns Rev 3 with a historically low bid in 2015. 

The Horns Rev wind farm was built in three phases, the first coming online in 2002, the second in 2009, and the third, Horns Rev 3, in 2019. Horns Rev 1, the first phase, was the first large-scale offshore wind farm in the world, with a capacity of 160 MW. 

Location

Horns Rev 3 is located in the North Sea 25-40 km off the Danish West Coast. The wind farm occupies an optimal wind area of 88 km², with the distance between turbines ranging between 1.1 km and 1.5 km. The turbines are installed in 11-19 m water depth on monopile foundations with separately installed transition pieces. The wind turbines are connected to an offshore substation (OSS) by 49 inter-array cables in 12 strings. In total approximately 100 km of infield array cable was installed in order to connect each of the 49 wind turbines to the OSS. The electricity generated by the turbines is transferred through 105 km of array cables to the transformer platform installed with three 33/220kV transformers. It is evacuated onshore via 34 km-long 220 kV export cables, before being transmitted through onshore cables to the existing substation at Endrup. Installation Base ports include Esbjerg (DK) and Thyboron (DK), whereas the Operations and Maintenance port is Hvide Sande (DK). 

Project Timeline

  • 22 August 2019: Horns Rev 3 was commissioned
  • January 2019: Final turbine installation completed
  • December 2018: First turbines begin delivering electricity to grid
  • July 2018: First turbine installed
  • October 2017: First foundation placed on seabed
  • May 2017: Construction begins
  • July 2016: Installation of three transformers
  • April 2015: Vattenfall awarded concession to build and operate Horns Rev 3 

Licensing Information

Regulatory oversight for Horns Rev 3 includes certification under Danish regulations. On February 10, 2021, DNV GL awarded a project certificate to Vattenfall’s Horns Rev 3 offshore wind farm in compliance with Danish Executive Order No. 73 (BEK 73). This certification verifies that the project meets all applicable national requirements for safety, environmental protection, and operational standards during wind farm deployment and operation. 

Key Environmental Issues

Noise impacts during construction, operation, and decommissioning have been quantified and are considered negligible due to the use of noise-reducing technology and adherence to mitigation protocols. Subsurface investigations identified complex Holocene sediment structures and regional variations in clay thickness, and informed geotechnical assessments. Marine monitoring has documented the role of Asterias rubens in regulating species composition and observed mobile species utilizing interstitial habitats near turbines. Mobile species such as gobies, blennies, and crabs have been observed foraging in seabeds between scour protections, contributing to ecosystem dynamics near the turbines. Atmospheric studies have recorded wind speed reductions upstream and wake effects, with no significant interference with radar or SAR systems, supported by low probabilities of failure in protection measures.