Skip to main content

Partnering with WREN, questionnaires are sent to offshore wind energy developers around the world who are involved in environmental monitoring. This page provides contextual project information and highlights environmental monitoring, providing links to available data and reports. Content is updated annually.

Revolution Wind

Description

Revolution Wind is America's first multi-state offshore wind project, currently under construction, that will provide 304 MW to Connecticut and 400 MW to Rhode Island (704 MW total). The wind farm will be composed of 65 11 MW Siemens Gamsea turbines. Local construction work began in 2023 and the wind farm is expected to be fully operational by 2026.

Revolution Wind is being developed by Ørsted and and Global Infrastructure Partners’ Skyborn Renewables. State Pier in New London in New London, and ProvPort and Quonset in Rhode Island will be used to support Revolution Wind along with other offshore wind industry projects throughout the region. 

Location

Revolution Wind will be located approximately 24 km from the Rhode Island coast and approximately 15 nautical miles offshore southeast of Point Judith, Rhode Island. Power generated by Revolution Wind will be transferred through a submarine transmission system, which will make landfall at Quonset Business Park in North Kingstown, Rhode Island. From there, one mile of underground transmission line will connect the landfall cable to a newly constructed substation (to be constructed and connected to the National Grid’s existing Davisville substation).

Project Timeline

  • Mar 2026: Power delivered to the grid
  • 2026, Jan 12: U.S. District Court for the District of Columbia issued decision to allow project to resume construction
  • 2025, Dec 22: Stop order issued by BOEM
  • 2024, December: All Conditions of COP Approval
  • 2024, September: First offshore wind turbine installed
  • 2023, November: Construction & Operations Plan Approval
  • 2023, August: BOEM Approval
  • 2023, May: Grid Connection Agreement executed
  • 2023, March: NOAA, Endangered Species Act Consultation Package Approval
  • 2023, March: Magnuson-Stevens Fishery Conservation and Management Act, Section 305 Essential Fish Habitat (EFH) Assessment Completion (NOAA)
  • 2023, March: Consultation pursuant to the Migratory Bird Treaty Act (MBTA) and Bald and Golden Eagle Protection Act
  • 2021, April and July: Site Investigations
  • 2020, June: Geological Surveys
  • 2019 - 2018: Site Investigations
  • 2017: BOEM approved the Site Assessment Plan (SAP) for Lease Area OCS-A 0486
  • 2014-2016: Site Investigations  

Licensing Information

At the federal level, the lead permitting agency, the Bureau of Ocean Energy Management (BOEM), approved the project’s Construction and Operations Plan in November 2023 after an extensive, multi-year review under the National Environmental Policy Act (NEPA) that included the National Marine Fisheries Service (NMFS), the U.S. Fish and Wildlife Service (FWS), the Army Corps of Engineers (USACE), U.S. Coast Guard (USCG), and the Department of Defense (DOD), among others. At the state level, the power-purchase agreement with Rhode Island Energy was approved by the Rhode Island Public Utilities Commission. In Connecticut, the project was selected via a competitive request for proposals process that is led by the state through the Connecticut Department of Energy & Environmental Protection. From there, power purchase agreements with the state’s regulated utilities (Eversource and United Illuminating) were negotiated and approved by the state’s Public Utilities Regulatory Authority (PURA).

Key Environmental Issues

Ørsted has conducted extensive environmental surveys up and down the East Coast. All ecological aspects of the wind farm have been investigated, and the results of those studies will be included in permit applications. Measures will be taken to minimize the ecological impact of the wind farm.