Skip to main content

Partnering with WREN, questionnaires are sent to offshore wind energy developers around the world who are involved in environmental monitoring. This page provides contextual project information and highlights environmental monitoring, providing links to available data and reports. Content is updated annually.

London Array

Description

At the time of its inauguration in 2013, RWE’s London Array offshore wind farm was the largest offshore wind farm in the world. It occupies and area of 107 square kilometres and has a capacity of 630 MW. Its 175 Siemens 3.6 MW turbines generate enough clean electricity to power around 500,000 British homes while displacing around 900,000 tonnes of CO2 a year.

Location

The London Array offshore wind farm is located 20km off the Kent coast in the Outer Thames Estuary. It is maintained and operated from the Port of Ramsgate and has a grid connection point of Cleve Hill.

Project Timeline

  • April 2023: Tenth Year in Operation
  • April 6, 2013: Fully Commissioned
  • October 2012: Construction Completed and power production began
  • July 1, 2011: 2 Offshore Substations installed
  • July 2009: Construction Started
  • August 2007: London Array project team was established
  • December 18, 2006: Offtake Conditionally Secured
  • June 2005: Applied for planning consent

Licensing Information

  • May 2009: Department of Energy and Climate Change (DECC), Formal Approval for phase 1
  • December 2008: Swale Borough Council, approval for the Cleve Hill substation
  • August 2007: United Kingdom NationalGrid, Onshore application
  • December 2006: FEPA, Offshore work consented

Key Environmental Issues

As part of the planning and licensing process for London Array, a series of environmental studies were carried out and reported on. The findings were summarised in the Environmental Statement (non-technical summary).

Various ecological mitigation measures were identified and agreed to safeguard the integrity of the project site. These measures are detailed in the Ecological Mitigation and Management Plan.

A three-year post-construction benthic monitoring programme was completed. This programme involved collection of grab and trawl samples at nearly 300 locations followed by all the associated microbenthic and Particle Size Distribution (PSD) sample analyses to test for potential impacts within the wind farm and in areas near the turbines themselves. A detailed analysis of datasets spanning the pre- and post-construction periods was subsequently conducted to validate the predictions made during the Environmental Impact Assessment