Skip to main content

OES-Environmental distributes metadata forms (questionnaires) to solicit information from developers involved in environmental monitoring around marine renewable energy project sites around the world. This page provides project descriptions, baseline assessment, post-installation monitoring, and links to available data and reports. Content is updated on an annual basis.

PacWave South Test Site

Description

PacWave is an open ocean wave energy testing facility at Oregon State University. It consists of two sites, PacWave North and PacWave South. 

PacWave South is permitted and is currently under construction. Once operational, PacWave South will offer pre-permitted, grid connected wave energy testing in a high-energy, open ocean environment. All necessary infrastructure including power/data cables, and an onshore grid connection station (known as the Utility Connection and Monitoring Facility, or UCMF) will be provided. The facility will be able to test up to 20 WECs, with a maximum power output of 20MW. The test site consists of four test berths, each with its own, dedicated, 5MW-rated power and data cable. 

The PacWave South facility has been developed in partnership with Oregon State University, U.S. Department of Energy, the State of Oregon, and local stakeholders. 

Information on the nearby PacWave North Test Site can be found on the metadata form here. 

Location

PacWave South is located 7 miles off the Pacific Coast near Newport, Oregon.

PacWave site location

 

Licensing Information

The PacWave South licensing process is complete and construction started on June 1, 2021. The Federal Energy Regulatory Commission (FERC) was the lead federal agency for the process and the PacWave South 25-year FERC license was issued in March, 2021. The Bureau of Ocean Energy Management (BOEM), U.S. Department of Energy, U.S. Army Corps of Engineers, National Parks Service and U.S. Coast Guard were cooperating agencies. 

Complete licensing information can be found on the FERC eLibrary website using docket number P-14616.

Project Progress

June 2013 – OSU submitted unsolicited request for research lease for PMEC-SETS project (now called PacWave South)
March 2014 – PMEC-SETS project officially commences with DOE funding (DOE award #DE-EE-0006518) 
June 2014 – FERC published a Notice of Intent to File License Application and approved OSU’s request to follow the Alternative Licensing Process
September 2018 – PMEC-SETS rebrands as PacWave South
May 2019 – Final License Application for PacWave South submitted
April 2020 – Environmental Assessment for PacWave South issued by FERC
February 2021 – BOEM Lease executed
March 2021 – FERC license issued
June 2021 – Underground construction at cable landing site start
May 2022 – Underground construction complete
April 2023 – Utility Connection and Monitoring Facility (UCMF) construction start. Expected completion by March 2025.
Summer 2024 – Subsea cable installation complete
Spring 2025 – PacWave South expected to be operational for grid-connected testing 

Key Environmental Issues

One of the key environmental concerns in the development process for PacWave South was the possibility of whale entanglement or entrapment with mooring lines. The disruption of animal behaviour and benthic habitat due to installation of cables undersea and onto shore also has received special consideration. The acoustic impacts of the project at multiple scales (installation, operation, vessel traffic) were also reviewed as a key issue. Many other potential impacts on species of concern were studied as part of the environmental assessment.