Description
A full-scale SmarTurbine prototype was built in 2010 with a 3 m diameter, 4.5 m length, 2.25 m rotor, 7 blades (2:1 tip speed ratio), and each weighing 3039 kg. The turbine was installed on a research surface platform that included instrumentation to allow the research team to evaluate performance by monitoring metrics such as stream velocity, electrical current, and voltage. The dock was hosted by the Dow Chemical Company and located in the Mississippi River at Plaquemine, Louisiana. The target flow was 2.25 m/s for 75% of the time at Scotlandville Bend.
Free Flow planned to install over 1000 MW of turbines across 53 permitted sites, with commercial arrays of around 120 turbines per site, with various riverbed pilings proposed.
Location
Mississippi River, near Baton Rouge, Louisiana.
Licensing Information
Of the 53 proposed projects, there were 5 “Lead Projects” that are using the Integrated Licensing Process (ILP) and the remaining 48 sites were approved to use the Traditional Licensing Process (TLP).
A series of 10 scoping meetings for the Lead Projects were held in April and May 2009, in Vicksburg, MS; New Orleans and Baton Rouge, LA; Memphis, TN; and St. Louis, MO; and written comments have been received.
In September and October 2009, Free Flow Power hosted four two-day meetings to discuss its Proposed Study Plan for the Lead Projects. Following those meetings, filing of written comments from stakeholders, Free Flow Power’s filing of a Revised Study Plan, and additional written comments, FERC issued a Study Determination on January 27, 2010. The study determination approved Free Flow Power’s proposed studies with substantial modifications, including requiring test deployments of mock or prototype turbines.
The U.S. Fish and Wildlife Service disputed aspects of the fish entrainment and related studies. The dispute resolution panel findings were filed on April 5, 2010.
Limitations at the test flumes led to further discussions of study approaches for fish entrainment mortality study approaches. Free Flow Power hosted a meeting at which FWS, FERC, and other agency staff discussed these issues.
The U.S. Army Corps of Engineers (Corps) had 4(e) mandatory conditioning authority for the navigation aspects of the project related to their responsibilities under the River and Harbors Act as carried out through the Federal Power Act.
Preliminary permits were officially surrendered on June 28, 2013.
Free Flow Power is no longer in business.
Complete licensing information can be found on the FERC eLibrary website using docket number P-12869.
Project Progress
Free Flow Power was founded in 2007, and conducted general research for a few years. In 2008, a proof of concept 1.4-meter turbine underwent flume tests that generated 10 kW in 3 m/s flow. In 2009, the 1.4-meter turbine was tested with a river deployment, which secured a $1.4 million grant from the US Department of Energy. In 2010, the 3-meter turbine was constructed and underwent flume tests that generated 40 kW in 3 m/s flow, while also testing fish survivability from collision. This same turbine was then installed on a barge in the Mississippi River on June 20th, 2011 and performed 6 months of trials. The results were encouraging, as the device performed as expected, with no discernible harm to river-dwelling fish.
A major drought experienced during 2012 produced record low-water conditions on parts of the Mississippi River, threatening commercial navigation on segments of the waterway and introducing conditions that affected the feasibility of turbine infrastructure locations that FFP had proposed at some of its hydrokinetic development sites. In conjunction with economic pressures in the electricity market, Free Flow Power conducted a feasibility evaluation and determined the sites were not feasible, resulting in a surrender of preliminary permits.
Key Environmental Issues
Among the environmental issues Commission staff anticipates analyzing in its EIS are the potential effects of the proposed projects on navigation, sediment deposition and dredging, recreation safety, fish strikes by turbines, avoidance of habitat near turbines by fish, threatened and endangered species, cultural and historic resources, wetlands, and terrestrial vegetation.