Description
Economic growth, climate change and security of energy supply underscore the global need for locally produced renewable energy. The ocean forms one of the largest yet least explored renewable energy sources on earth. The HiWave-5 project aims at demonstrating breakthrough wave technology that can enable Levelized Cost of Energy (LCOE) competitive with established energy sources in the near future when deployed in moderate volumes. The project’s overall goal is to successfully demonstrate 3rd -party certified Wave Energy Converter (WEC) products that makes wave energy bankable in the market by 2024, allowing end users to secure mainstream infrastructure/renewable energy project finance for pre-commercial arrays. This will be achieved through two stages:
- Demonstration and prototype certification of single device full scale (C4) WEC
- Demonstration and type certification of pilot array with three (C5) WECs.
The project partners consider the Aguçadoura site in northern Portugal to be well suited for the demonstrations.
Location
The site is located approximately 5.5km offshore in Agucadoura, North of Porto, Portugal, (41.458744°, -8.842233°).
Licensing Information
The license process was submitted through DGRM - General-Directorate for Natural Resources, Security and Maritime Services. As an organization DGRM are the single point of contact for marine applications within Portugal, this agency then contacts other relevant national bodies which need to be involved in the consenting process. Successful completion of all steps within the process and the project deemed to meet the requirements to be issued consent and a TUPEM (Permits for Private Use of the National Maritime Space) document was issued by DGRM.
Grid reservation is assured, and production license is obtained for the 1.2MW and will be valid up to 2030.
Project Progress
The project timeline is shown below, CorPower Ocean have taken a five-stage approach to commercializing wave energy, this began with small prototype validation tests at tank test scale, a third scale system test, a half scale device ocean deployment and stage 4 our HiWave-5 full scale ocean demonstration. Following a single device being put into operation stage 5 is to install a further three devices. On completion of the array being validated we will then proceed to install multi megawatt farms on several sites around the world.
Phase 1 – C4 Full Scale Single device installed – Q4 2022 / Q1 2023
Phase 2 – C5 Full Scale Multiple devices installed, (up to four devices) – 2024/2025
Key Environmental Issues
The main environmental issues taking into consideration include but not limited to the following:
- Disturbance/Displacement of marine mammals and bird in the area.
- Acoustic impact from increased vessel traffic onsite and other activities.
- Biofouling and non-native species introduction
- Habitat creation
- Habitat removal
The above list are the key areas in which we have reviewed and included within our system design process, our goal is to minimise the impact on the natural environment and the animals within is whilst creating a cost-effective source of clean electrical power.
Baseline Assessment: CorPower Ocean HiWave-5 Project
Receptor | Study Description | Design and Methods | Results | Status |
---|---|---|---|---|
Marine Mammals | WavEC Environmental Monitoring Campaign The monitoring plan considers that visual and acoustic monitoring will be carried out, during a period of 4 years, starting one year before deployment and 3 years during the operation since the first device is operational. The mammal monitoring campaigns carried out by WavEC during the period 2021-2024 are covered under the EU-SCORES H2020 project. https://www.safewave-project.eu/about-the-project/ | All to ISO9001 Acoustic monitoring Campaign (Mammal Noise) The equipment used is F-POD, an autonomous datalogger for detection of cetacean spices. Two F-PODs are deployed in the site. One is located within the boundaries of our deployment area (impact area) and another is located at 1.5 km away (control area). Data from both are compared to assess the impacts of HiWave-5. | NA | Baseline data currently being analysed by WavEC. Release date end of 2022. |
Marine Mammals | WavEC Environmental Monitoring Campaign The monitoring plan considers that visual and acoustic monitoring will be carried out, during a period of 4 years, starting one year before deployment and 3 years during the operation since the first device is operational. https://www.safewave-project.eu/about-the-project/ | All to ISO9001 Visual observation Campaign Observers are certified as marine mammal observers or have experience as marine mammal observers proven by CV. Observers will use binoculars to confirm sightings details (e.g. number of animals, species). Observations are carried out three times a year during the periods of April-May, June-August, October-November. They are conducted in the deployment site (impact area) and throughout several kilometers around (control area). Data from all observation methods is then compared to assess the impacts of HiWave-5. | NA | Baseline data currently being analysed by WavEC. Release date end of 2022. |
Physical Environment | Seabed integrity inspection with ROV of seabed before and after pile install + intermittently during operation and after decommissioning. Performed under the SafeWave EMMF project. https://www.safewave-project.eu/ | ROV videos and footage taken during the cable layout campaign and pile installation. Shared to WavEC for analysis. | NA | Baseline data currently being analysed by WavEC and AZTI. |
Marine Mammals | Underwater noise characterization of the WEC devices to understand their acoustic impacts. Performed under the SafeWave EMMF project. https://www.safewave-project.eu/ | Collected with three hydrophone devices located in different points within the project deployment area. A monitoring period takes place both during spring/summer and autumn/winter seasons, with 48 hours for a continuous sampling. There is one baseline monitoring period in HiWave-5 before the installation of the first C4 WEC (2022). | NA | Baseline data currently being analysed by WavEC. Release date end of 2022. |
Post-Installation Monitoring: CorPower Ocean HiWave-5 Project
Stressor | Receptor | Study Description | Design and Methods | Results | Status |
---|---|---|---|---|---|
Noise | Marine Mammals | Underwater noise characterization of the WEC devices to understand their acoustic impacts. Performed under the SafeWave EMMF project. | Collected with three hydrophone devices located in different points within the project deployment area. A monitoring period takes place both during spring/summer and autumn/winter seasons, with 48 hours for a continuous sampling. There are two post operational monitoring periods in HiWave-5. One after the installation of the first C4 WEC (2023) and another after the entry into operation of the three C5 WECs (2024). | NA | Planned – Starting to be collected in Q1 2023 post WEC deployment. |
Noise | Marine Mammals | Underwater and onshore EMF measurements performed on both the WEC umbilical and the seafloor cable. Performed under the SafeWave EMMF project. | One campaign performed with the Autonomous Underwater Vehicle (AUV) COMET-300 developed by RTSYS equipped with an EMF sensor. Measurements will be done around the WEC umbilical cables in the water column and around cables laid in the seafloor in at least 5 sampling stations. Samplings will be done at 10 m, 7 m, and 5 m distance from the cables. | NA | Planned – Starting to be collected in Q1 2023 post WEC deployment. |
Habitat Change | Marine Mammals | Visual observation Campaign Observers are certified as marine mammal observers or have experience as marine mammal observers proven by CV. Observers will use binoculars to confirm sightings details (e.g. number of animals, species). In parallel to the officially approved methodology, the EU-SCORES project is introducing and demonstrating the use of human piloted drones in aerial inspection of mammals post-operation. | Observations are carried out three times a year during the periods of April-May, June-August, October-November. They are conducted in the deployment site (impact area) and throughout several kilometers around (control area). Data from all observation methods is then compared to assess the impacts of HiWave-5. | NA | Planned – Starting to be collected in Q1 2023 post WEC deployment. |
Noise | Marine Mammals | Acoustic monitoring Campaign (Mammal Noise). | The equipment used is F-POD, an autonomous datalogger for detection of cetacean species. Two F-PODs are deployed in the site. One is located within the boundaries of our deployment area (impact area) and another is located at 1.5 km away (control area). Data from both are compared to assess the impacts of HiWave-5. | NA | Planned – Starting to be collected in Q1 2023 post WEC deployment. |
Displacement | Marine Mammals | Visual observation Campaign Observers are certified as marine mammal observers or have experience as marine mammal observers proven by CV. Observers will use binoculars to confirm sightings details (e.g. number of animals, species). In parallel to the officially approved methodology, the EU-SCORES project is introducing and demonstrating the use of human piloted drones in aerial inspection of mammals post-operation. | Observations are carried out three times a year during the periods of April-May, June-August, October-November. They are conducted in the deployment site (impact area) and throughout several kilometers around (control area). Data from all observation methods is then compared to assess the impacts of HiWave-5. | NA | Planned – Starting to be collected in Q1 2023 post WEC deployment. |