Skip to main content

OES-Environmental distributes metadata forms (questionnaires) to solicit information from developers involved in environmental monitoring around marine renewable energy project sites around the world. This page provides project descriptions, baseline assessment, post-installation monitoring, and links to available data and reports. Content is updated on an annual basis.

CorPower Ocean HiWave-5 Project

Description

Economic growth, climate change and security of energy supply underscore the global need for locally produced renewable energy. The ocean forms one of the largest yet least explored renewable energy sources on earth. The HiWave-5 project aims at demonstrating breakthrough wave technology that can enable Levelized Cost of Energy (LCOE) competitive with established energy sources in the near future when deployed in moderate volumes. The project’s overall goal is to successfully demonstrate 3rd -party certified Wave Energy Converter (WEC) products that makes wave energy bankable in the market by 2027/2028, allowing end users to secure mainstream infrastructure/renewable energy project finance for pre-commercial arrays. This will be achieved through two stages: 

  1. Demonstration and prototype certification of single device full scale (C4) WEC 
  2. Demonstration and type certification of pilot array with three (C5) WECs. 

The project partners consider the Aguçadoura site in northern Portugal to be well suited for the demonstrations.
 

Location

The site is located approximately 5.5km offshore in Agucadoura, North of Porto, Portugal, (41.458744°, -8.842233°).

Licensing Information

The license process was submitted through DGRM - General-Directorate for Natural Resources, Security and Maritime Services. As an organization DGRM is the single point of contact for marine applications within Portugal, this agency then contacts other relevant national bodies which need to be involved in the consenting process. Successful completion of all steps within the process and the project deemed to meet the requirements to be issued consent and a TUPEM (Permits for Private Use of the National Maritime Space) document was issued by DGRM.

Grid reservation is assured, and production license is obtained for the 1,2MW and is valid up to 2030.

Project Progress

The initial project timeline is shown below, CorPower Ocean have taken a five-stage approach to commercializing wave energy, this began with small prototype validation tests at tank test scale, a third scale system test, a half scale device ocean deployment and stage 4 our HiWave-5 full scale ocean demonstration. Following a single device being put into operation, stage 5 is to install a further three devices. On completion of the array being validated we will then proceed to install multi megawatt farms on several sites around the world. 

Stage 4 and 5 demonstration phases project schedule
Stage 4 and 5 demonstration phases project schedule

 

 

 

 

 

 

 

 

 

 

Phase 1 – C4 Full Scale Single device installed – Q3 2023-2026
Phase 2 – C5 Full Scale Multiple devices installed (up to four devices) – 2026/2027

Key Environmental Issues

The main potential environmental issues taken into consideration include but not limited to the following: 

  • Disturbance/Displacement of marine mammals and birds in the area.
  • Acoustic impact from increased vessel traffic onsite and other activities.
  • Biofouling and non-native species introduction
  • Habitat creation
  • Habitat removal 

The above list are the key areas in which we have reviewed and included within our system design process, our goal is to minimize the impact on the natural environment and the animals within is whilst creating a cost-effective source of clean electrical power.