Skip to main content

Partnering with WREN, questionnaires are sent to offshore wind energy developers around the world who are involved in environmental monitoring. This page provides contextual project information and highlights environmental monitoring, providing links to available data and reports. Content is updated annually.

Sunrise Wind

Description

Sunrise Wind will be composed of 95 Siemens Gamesa turbines with an installed capacity of approximately 924 MW. The potential capacity of the wind farm will be enough to power nearly 600,000 homes. Sunrise Wind is expected to be operating in 2027. Sunrise Wind will support approximately 800 jobs through the project’s development, construction, and operation. 

Location

The Sunrise Wind Lease Area covers approximately 86,823 acres and is located in federal waters approximately 30.4 km south of Martha’s Vineyard, Massachusetts and approximately 48.1 km east of Montauk, New York, and 26.8 km from Block Island, Rhode Island. The planned interconnection point is the Holbrook and West-Bus substation in the town of Brookhaven within the Long Island Power Authority’s (LIPA) service territory. The offshore export cables would be buried below the seabed in federal and New York State waters.

Project Timeline

  • 2027: Projected Commissioning date
  • 2024, July: Construction began
  • 2024, June: Construction and Operations Plan approved
  • 2023, February: Public Consultation Window on the Draft Environmental Impact Statement
  • 2022, December: BOEM Announced Availability of the Draft Environmental Impact Statement
  • 2022, November: New York State PSC Approval
  • 2022, June: NPS Permit Application Deemed Complete
  • 2021, October: Geophysical Surveys and Site Investigations
  • 2021, May: Construction and Operations Plan Submitted
  • 2021, April: Geophysical Survey along Export Cable
  • 2021, March: Issuance of Commercial Lease of Submerged Lands for Renewable Energy Development on the OCS
  • 2020, February-March: Geophysical Surveys and Site Investigations
  • 2019, July: Offtake Conditionality Secured
  • 2013, July: Site Exclusivity 

Licensing Information

The Sunrise Wind project pursued comprehensive licensing and permitting across federal and state agencies throughout 2022 and 2023. In 2022, the project filed multiple permits, including the Environmental Management and Construction Plan with the New York State Department of Public Service, Clean Water Act Section 404 and Rivers and Harbors Act permits with the U.S. Army Corps of Engineers, and an Outer Continental Shelf Air Permit with the U.S. EPA. The project obtained the National Park Service Right-of-Way and Special Use Permits and filed utility work permits with the New York State Department of Transportation. Throughout 2022, the project completed consultations and received certifications from multiple New York State agencies. In 2023, the project secured the NOAA Incidental Take Authorization in February and the U.S. Fish and Wildlife Service Endangered Species Act Consultation Package Conclusion in June, advancing its regulatory compliance process. On June 6, 2023, extensions were approved for the NEPA, COP, Section 106, MMPA (NOAANMFS), Sections 10/404/408 (USACE), NPS Permit, Clean Water Act Section 402 (EPA), and OCS Air Permit (EPA). Further extensions for COP, NPS, Section 10/404, Section 408, OCS Air Permit, and NPDES completion dates were granted on February 2, 2024. As of July 2024, Sunrise Wind has officially completed federal environmental review and permitting through the Permitting Council’s FAST-41 program.