Skip to main content

Partnering with WREN, questionnaires are sent to offshore wind energy developers around the world who are involved in environmental monitoring. This page provides contextual project information and highlights environmental monitoring, providing links to available data and reports. Content is updated annually.

Maryland Offshore Wind (MarWin)

Description

US Wind holds the lease rights to a federal lease area with the western edge located approximately 16.2 km to the closest point on the Maryland coastline. The lease area, about 80,000 acres in size, has a capacity for US Wind’s contracted projects of about 1,710 megawatts (MW) of offshore wind energy, which is enough clean electricity to power 600,000 homes while displacing 4 million tons of CO2 every year. 


The Maryland Offshore Wind Project is likely to be built in multiple construction campaigns. The first will be MarWin consisting of approximately 400 MW generating approximately 1.6 million megawatt-hours (MWh) per year. The following phases, totaling 1.3 GW for Momentum Wind, would be built out over the subsequent years (early 2030’s). Once fully built out, electricity from the lease area would total nearly 7 million MWh every year.


The full buildout of the Maryland Offshore Wind Project within the federal lease area would include 114 WTGs, four offshore substations and one meteorological tower. The project will be interconnected by up to four (4) 230-275 kV export cables into US Wind onshore substations adjacent to the Indian River Power Plant in Dagsboro, Delaware. 

Location

The Project will be located approximately 16.2 km from the Maryland coastline. It will have an installation base in Baltimore, Maryland and a grid connection point near the Indian River power plant in Dagsboro, Delaware (USA).

Project Timeline

  • 2025, January: Maryland Offtake Re-bid Conditionally Secured (MarWin and Momentum Phases)
  • 2024, December: BOEM Approves COP
  • 2024, September: BOEM Announces Record of Decision
  • 2024, July: Final Environmental Impact Statement Available
  • 2023, September: Draft Environmental Impact Statement Available
  • 2022, June: Section 106 Review/Consultation with SHPO/THPO Initiated
  • 2021, December: Maryland Offtake Conditionally Secured (Momentum)
  • 2021, May: BOEM Site Assessment Plan (SAP) Approved
  • 2020, August: COP Submitted
  • 2017, May: Maryland Offtake Conditionally Secured (MarWin)
  • 2016, January: BOEM Site Assessment Plan (SAP) Submitted
  • 2015, August: Initial Interconnection Request Submitted
  • 2014, August: Site Exclusivity Obtained
  • 2014, July: BOEM Final Sale Notice (FSN) Issued

Licensing Information

Construction and Operations Plan (COP)

  • COP submitted to BOEM August 2020
  • BOEM approves COP December 2024

National Environmental Policy Act (NEPA) review 

  • BOEM Notice of Intent to prepare an Environmental Impact Statement (EIS) posted in Federal Register June 2022
  • BOEM Draft EIS issued September 2023
  • Maryland Department of the Environment (MDE)/Maryland Department of Natural Resources (MDNR) federal consistency concurrence with Maryland enforceable coastal policies issued under Subpart E of the Coastal Zone Management Act (CZMA) in support of BOEM’s COP and EIS July 2024
  • Delaware Department of Natural Resources and Environmental Control (DNREC) issued conditional concurrence under Subpart E of the CZMA that BOEM’s COP and EIS for the US Wind project is consistent with DNREC’s Delaware Coastal Zone Management Program (DCMP) enforceable policies July 2024
  • BOEM Final EIS issued July 2024
  • BOEM issues Record of Decision (ROD) September 2024

Section 10 Rivers and Harbors Act/Section 404 Clean Water Act

  • United States Army Corps of Engineers (USACE) Individual Permit Section (10/404) application submitted August 2023
  • Joint Federal/State Application for the Alteration of Any Tidal Wetland in Maryland submitted to MDE August 2023
  • Water Quality Certification (per Clean Water Act Section 401) request submitted to MDE February 2024
  • Water Quality Certification request submitted to DNREC April 2024
  • MDE Water Quality Certification issued July 2024
  • MDE/ MDNR Conditional federal consistency with Maryland enforceable coastal policies issued under Subpart D of the CZMA in support of USACE Section10/404 permit July 2024
  • DNREC issued conditional concurrence under Subpart D of the CZMA that the USACE’s Section 10/404 permit for the US Wind Project is consistent with DNREC’s DCMP enforceable policies July 2024
  • DNREC Water Quality Certification issued October 2024
  • Maryland Tidal Wetlands License issued by the Maryland Board of Public Works November 2024
  • USACE Individual Permit (10/404) issued January 2025

Section 408 Permit Permission-Civil Works Projects

  • USACE Section 408 application submitted August 2023
  • USACE Section 408 Permit Permission issued January 2025

National Historic Preservation Act (NHPA) Section 106 Consultation

  • BOEM initiates Section 106 consultation with State Historic Preservation Offices/Tribal Historic Preservation Offices June 2022
  • BOEM Final Section 106 Memorandum of Agreement with Consulting Parties August 2024

Marine Mammal Protection Act - Incidental Take Request/Letter of Authorization (LOA) 

  • National Marine Fisheries Service (NMFS) LOA deemed complete April 2023
  • NMFS publication of Draft Rule in Federal Register for LOA January 2024
  • NMFS publication of Final Rule in Federal Register for LOA October 2024
  • NMFS LOA issued November 2024

Magnuson-Stevens Fishery Conservation and Management Act-Essential Fish Habitat Consultation

  • NMFS Essential Fish Habitat (EFH) Consultation Request submitted by BOEM June 2023
  • NMFS EFH Conservation Recommendations issued May 2024

Endangered Species Act Section 7 Consultation

  • NMFS Section 7 Endangered Species Act (ESA) Consultation Request submitted by BOEM June 2023
  • United States Fish and Wildlife Service (USFWS) Section 7 ESA Consultation Request submitted by BOEM June 2023
  • USFWS Section 7 ESA BiOp issued May 2024
  • NMFS Section 7 ESA Biological Opinion (BiOp) issued June 2024

Obstruction Evaluation/Airport Airspace Analysis (OE/AAA)-Determination of No Hazard

  • OE/AAA filed with Federal Aviation Administration (FAA) October 2022
  • FAA Determination of No Hazard (DNH) received May 2023
  • FAA DNH Extension granted January 2025

Outer Continental Shelf Clean Air Act Permit

  • Outer Continental Shelf (OCS) Clean Air Act Air Permit Application submitted to Maryland Department of the Environment (MDE) August 2023
  • MDE Final OCS Clean Air Act Permit to Construct, New Source Review Approval, and Prevention of Significant Deterioration Approval issued June 2025

DNREC Wetlands Permit

  • Wetlands Permit Application submitted to DNREC February 2024
  • Wetlands Permit approved December 2024

DNREC Subaqueous Lands Permit and Lease

  • Subaqueous Lands Permit and Lease Application submitted to DNREC February 2024
  • Subaqueous Lands Permit and Lease approved December 2024

DNREC Beach Preservation Coastal Construction Permit

  • Beach Preservation Coastal Construction Permit Application submitted to DNREC February 2024
  • Beach Preservation Coastal Construction Permit approved December 2024

DNREC Division of Parks and Recreation Special Use Permit for underground utilities through State park

  • DNREC issued Beach lease January 2025

Key Environmental Issues

Careful siting of the offshore wind lease area avoids many environmental issues related to the Maryland Offshore Wind Project.

  • The seabed within US Wind’s lease area is primarily comprised of soft sandy bottom areas.
  • Commercial fishing largely occurs elsewhere, as demonstrated through revenue of less than $200,000 annually on average from the lease area. Fishing would continue throughout the lease area and the reef effect related to the increased underwater structure is likely to attract numerous fish.
  • Few bats have been detected in the lease area, and the relatively low numbers of birds are species that would not be flying at heights to interact with the wind turbines. 

Notwithstanding the generally minor potential impacts, US Wind proposed extensive mitigation measures to further avoid and minimize impacts to environmental resources and marine wildlife through the development of the Maryland Offshore Wind Project. These mitigation measures are now incorporated in the comprehensive permits and approvals issued for its Project.

US Wind conducts wildlife studies and surveys to supplement and complement existing research by agencies and academic institutions like the Bureau of Ocean Energy Management, University of Maryland Center for Environmental Science, and Maryland Department of Natural Resources.

For example, US Wind recently partnered with University of Maryland Center for Environmental Science (UMCES) on two efforts to further understand whale presence in the Lease area and potential impacts. These include a real-time whale detection system to provide timely alerts on the presence of baleen whales (North Atlantic right whales, and humpback, fin and sei whales) using specialized quiet mooring technology, whale vocalization detection algorithms, and telecommunications to transmit frequent alerts on the presence of baleen whales. A Passive Acoustic Monitoring (PAM) Array will also utilize two types of listening devices to determine the presence and migration patterns of large whales, dolphins, and porpoises. In addition, UMCES has commenced commercial fisheries resource monitoring survey work focused on the economically important black sea bass fishery as well as a recreational fishery resource monitoring survey. More information on the UMCES research and monitoring efforts can be found on the UMCES’ Tailwinds web page

US Wind is also conducting an additional avian monitoring program to confirm earlier conclusions about risks and potential impacts. The avian monitoring program is comprised of data collection from sensors on the Metocean Buoy deployed by US Wind in May 2021 through May 2024, as well as pre- and post-construction aerial surveys over the Lease area, including a 10-kilometer buffer.

US Wind has released fact sheets with additional information on how they plan to protect marine mammalswildlife, and birds before, during, and after construction.