Skip to main content

Partnering with WREN, questionnaires are sent to offshore wind energy developers around the world who are involved in environmental monitoring. This page provides contextual project information and highlights environmental monitoring, providing links to available data and reports. Content is updated annually.

Coastal Virginia Offshore Wind (CVOW)

Description

Coastal Virginia Offshore Wind (CVOW) consists of a 2-turbine pilot, which became operational in October 2020, and a 2.6 GW commercial-scale project, which is currently under construction. The pilot is located 27 miles off the coast of Virginia Beach and is the first offshore wind farm installed in federal waters and the first offshore wind project developed and owned by an electric utility company (Dominion Energy). The commercial-scale project will expand to include 176 turbines, 3 offshore substations, and 9 buried offshore export cables extending to an onshore cable landing area. The project, scheduled to be completed in 2026, is expected to generate enough electricity to power 660,000 homes.

View photos of CVOW’s construction on the BOEM CVOW Flickr page.

Location

The project is located in federal waters 27 miles off the coast of Virginia Beach, Virginia (USA).

Project Timeline

  • 2025-2026: Project construction and commissioning
  • March 2025: First offshore substation installed
  • November 2024: 78 monopile foundations and 4 offshore substation foundations were installed
  • November 2023: Transmission construction started
  • 2023: BOEM Record of Decision
  • September 2023: Final Environmental Impact Statement Issued
  • 2022: CVOW approved by Virginia State Corporation Commission (SCC)
  • 2022: Virginia State Corporation Commission review
  • 2020: Pilot project turbines installed
  • 2020: Construction and Operations Plan (COP) submitted to BOEM
  • 2019: BOEM approves RAPR
  • 2017: Submission of Research Activities Plan Revision (RAPR) for BOEM’s Review
  • 2017: Ørsted retained as EPC contractor for the project
  • 2017: Site assessment plan approved by BOEM
  • 2013: Dominion Energy executed lease agreement with Bureau of Ocean Energy Management (BOEM)

Licensing Information

The Coastal Virginia Offshore Wind Commercial (CVOW-C) Project acquired a competitive lease on September 4, 2013, where Dominion Energy was identified as the winner of Lease Area OCS-A 0483, covering 112,799 acres located 23.5 nautical miles offshore Virginia in federal waters. In 2022, the project submitted critical permit applications, including the FAA Form 7460-1 for construction notice in April (with determinations received in May), an initial Clean Air Act Outer Continental Shelf (CAA OCS) Air Permit in March, and comprehensive Clean Water Act (CWA) and Rivers and Harbors Act (RHA) applications in May. The project received a Record of Decision from the Department of the Interior on October 31, 2023, and the Bureau of Ocean Energy Management (BOEM) provided final Construction and Operations Plan approval on January 28, 2024, authorizing the construction of 176 wind turbines and three offshore substations.

More information can be found on the BOEM Permitting & Documents page.

Key Environmental Issues

Prior to constructing the pilot turbines, more than two dozen studies and surveys were conducted to ensure protection of ocean life and avian species. The data and lessons learned from those studies are informing the development of the commercial project. 

CVOW is the second facility to be studied under BOEM’s Realtime Opportunity for Development Environmental Observations (RODEO) program. RODEO aims to make direct, real-time measurements of the nature, intensity, and duration of potential stressors during the construction and initial operations of selected offshore wind facilities. Underwater acoustic monitoring was conducted during the construction of two monopile wind turbines (one with a bubble curtain and one with a double bubble curtain).

Additionally, Dominion contracted with Normandeau Associates Inc. to provide postconstruction monitoring for the pilot turbines. Normandeau's Acoustic and Thermographic Offshore Monitoring (ATOMTM) systems are deployed on platforms underneath the two turbines. They collect thermographic and natural light imagery within the rotor swept zone and the vicinity of the wind turbine 24/7 during the monitoring period. Additional ATOMTM sensors include bird and bat acoustics and VHF/MOTUS Nanotag receivers and antennae. Normandeau also conducted six boat-based surveys every other month during the first year of operations using a transect design. Additional information on this monitoring can be found here