Description
Multiple ORPC power systems have been tested at the Cobscook Bay test site. ORPC initially tested and commercially operated its TidGen® Power System (TidGen) at the site in 2012-2013. The core component of the TidGen is ORPC’s proprietary turbine generator unit (TGU). The TGU utilized four advanced design crossflow (ADCF) turbines to drive a permanent magnet generator mounted between the turbines on a common driveshaft. The TGU was 30 meters in length (98 feet), 5 meters high (17 feet), and 5 meters wide (17 feet). It was attached to a bottom support frame, which held the TGU in place approximately 4.5 meters (15 feet) above the sea floor. The bottom support frame is 30 meters long (98 feet) by 15 meters wide (50 feet) by 4.5 meters high (15 feet) and secured to the seafloor with ten 30-inch diameter stell piles. The bottom support frame is constructed of steel, and the TGU was constructed of steel and composite material. The coupled TGU and bottom support frame comprised the TidGen device. The TidGen device was connected to an underwater power consolidation module, which was then connected to an onshore station through a single underwater power and data cable. Power from this device was delivered to shore and incorporated into the local electrical distribution system. The TidGen TGU was removed from the site in 2013 and the bottom support frame remained on site to allow for continued test activities.
ORPC also tested its OCGen® Module Mooring System (OCGen) at the Cobscook Bay test site in 2014. The prototype OCGen device consisted of a buoyancy pod attached to a chassis with two turbines placed in the water column 10 meters (35 feet) below mean low water. It had no generator and was not grid connected. The turbines were re-used from a previous turbine model. The device was secured using gravity anchors and a tension-leg mooring system. The OCGen was removed from the site after almost three months of testing.
ORPC’s next generation, full-scale TidGen® Power System is presently under development and partially funded by the U.S. Department of Energy (DOE) Water Power Technologies Office (WPTO). A single TidGen system is rated at 80 kilowatts (kW) of output at 2.25 meters per second (m/s) of water velocity, with a peak output of 160 kW at 3.5 m/s of velocity. The approximate dimensions of a TidGen device will be 17.8 meters wide (58 feet) by 6 meters high (20 feet). Prior to testing a full-scale iteration of the TidGen device, ORPC tested a single turbine TidGen system during summer 2023 in Cobscook Bay. Information gathered during the single turbine TidGen test phase is being utilized to complete designs, installation plans, and buildout for the full scale TidGen device.
Device/Array Installation Date:
TidGen® Power System: September 13, 2012
OCGen® Module Mooring System: June 27, 2014
Single Turbine TidGen® System: May 28,2023
Device/Array Removal Date:
TidGen® Power System: July 15, 2013
OCGen® Module Mooring System: September 17, 2014
Single Turbine TidGen® System: September 20, 2023
Location
The site is located in Cobscook Bay on State of Maine submerged lands, near Eastport and Lubec, Maine, United States.
Licensing Information
ORPC obtained a Federal Energy Regulatory Commission (FERC) Preliminary Permit for the Cobscook Bay and Western Passage Project sites on July 23, 2007. On January 13, 2011, FERC issued a successive Preliminary Permit for ORPC’s continued research specifically for the Cobscook Bay site. Feasibility studies, including environmental surveys, and pre-filing consultation were conducted, resulting in ORPC’s filing of a draft pilot project license application with FERC on July 24, 2009 and subsequently, the final pilot project license application on September 1, 2011. ORPC received a FERC pilot project license for the Cobscook Bay Tidal Energy Project on February 27, 2012 (FERC Project No. P-12711).
While the Cobscook Bay site serves as an excellent device testing area, ORPC has determined that the tidal current velocities at the site do not justify pursuing a commercial FERC license for the site at this time. In a March 14, 2017 submittal to FERC, ORPC stated that it did not intend to move on to the next step in the licensing process to file a notice of intent (NOI) or a Pre-Application Document (PAD) to commercially license the project. On January 26, 2022, ORPC filed documentation evidencing completion of Cobscook Bay Tidal Energy Project removal and site restoration activities. The FERC pilot license is now closed.
In accordance with FERC order dated November 19, 2021, ORPC gained permission to maintain the Cobscook Bay bottom support structure to allow for continued testing of next generation tidal energy devices at the Cobscook Bay site. Federal agency jurisdiction presiding over continued use of the Cobscook Bay site and the associated bottom support structure has been transitioned from FERC to the U.S. Army Corps of Engineers (USACE). As such, the bottom support frame remains in place to allow for continued device testing activities.
Complete licensing information can be found on the FERC eLibrary website using docket number P-12711.
Project Progress
In March 2012, ORPC began construction at the Cobscook Bay site. A single-device TidGen Power System with a rated capacity of 150 kW was secured to the bottom support frame, which was fully installed with piles driven on April 8, 2012. The TGU was deployed on August 14, 2012. Subsea power and data cables were deployed on the seafloor and connected to the TidGen device.
The TidGen Power System delivered electricity to the grid from September 2012 to July 2013. This was the first grid-connected installation of an ORPC power system. Electricity generated by the TidGen Power System was delivered by an underwater power cable to an onshore station in Lubec, Maine, where it was power-conditioned and connected to the Bangor Hydro Electric Company (now Versant Power) utility grid on September 13, 2012. ORPC entered into a 20-year agreement with Bangor Hydro Electric Company on January 1, 2013, for up to 5 megawatts at a price of $215/MWh, escalating at 2.0% per year. The project provided numerous lessons learned related to installation, maintenance, and retrieval. For retrieval a novel catamaran barge system was utilized that significantly reduced cost of operation. The TGU was transported to shore, placed on blocking, and lifted onto a trailer for transfer to concrete blocking pads on July 16, 2013.
In 2014, the OCGen Module Mooring System was deployed at the Cobscook Bay site. This system was designed to demonstrate the feasibility of a floating tensioned mooring system operating in a reversing flow tidal environment which could expedite future device installations and improve water column siting. The mooring system was installed from June 27, 2014 to September 17, 2014 and turbines rotated from July 24 to August 10, 2014. The results of this test have informed ORPC’s latest TidGen power system designs, as a similar tensioned mooring system design is being utilized for TidGen.
A subscale of ORPC’s latest TidGen System, the single turbine TidGen system, was developed with assistance from the DOE WPTO and tested from June 2023 – September 2023. The Cobscook Bay site was not grid connected during these testing exercises.
Key Environmental Issues
The following table includes a list of the federal and/or state listed threatened (T) and endangered (E) species with potential to occur in the Cobscook Bay test site area.
|
Common Name |
Scientific Name |
Federal Status |
State Status |
| Birds | |||
| Roseate Tern | Sterna dougallii dougallii |
E |
E |
| Terrestrial Mammals | |||
| Northern Long-eared Bat | Myotis septentrionalis |
T |
E |
| Fish | |||
| Shortnose Sturgeon | Acipenser brevirostrum |
E |
E |
| Atlantic Sturgeon (Gulf of Maine DPS) | Acipenser oxyrinchus oxyrinchus |
T |
N/A |
| Atlantic Sturgeon (New York Bight, Chesapeake Bay, Carolina, and South Atlantic DPS) | Acipenser oxyrinchus oxyrinchus |
E |
N/A |
| Atlantic Salmon (Gulf of Maine DPS) | Salmo salar |
E |
N/A |
| Aquatic Reptiles | |||
| Green Sea Turtle (N Atlantic DPS) | Chelonia mydas |
T |
N/A |
| Kemp’s Ridley Sea Turtle | Lepidochelys kempi |
E |
E |
| Leatherback Sea Turtle | Dermochelys coriacea |
E |
E |
| Loggerhead Sea Turtle (NW Atlantic DPS) | Caretta caretta |
T |
T |
| Marine Mammals | |||
| Sei Whale | Balaenoptera borealis |
E |
E |
| Fin Whale | Balaenoptera physalus |
E |
E |
| North Atlantic Right Whale | Eubalaena glacialis |
E |
E |
| Sperm Whale | Physeter macrocephalus |
E |
E |
| Humpback Whale | Megaptera novaeangliae |
DL |
E |
ORPC designed and carried out the following monitoring plans over the course of the FERC licensing process and as part of FERC license compliance to ascertain the Cobscook Bay Tidal Energy Project’s environmental effects:
- Acoustic Monitoring
- Benthic and Biofouling Monitoring
- Fisheries and Marine Life Interaction Monitoring
- Hydraulic Monitoring
- Marine Mammal Monitoring
- Sea and Shorebird Monitoring
In addition, as required by ORPC’s FERC pilot license, an Adaptive Management Plan was implemented to outline and manage the process for evaluating environmental monitoring data and license modifications where appropriate. An Adaptive Management Team was created and was comprised of jurisdictional federal and state agencies, and ORPC. The team met on an annual basis over the course of the FERC license to review project updates, project operations, study results, and proposed study plans.
ORPC Environmental Webpage: https://orpc.co/project-monitoring/