Description
New England Wind 1, formerly known as Park City Wind, together with New England Wind 2, formerly known as Commonwealth Wind, will form part of a 1,870 MW wind farm complex. New England Wind 1 will have an installed capacity of 791 MW and New England Wind 2 will have an installed capacity of 1.1+ GW. On May 15, 2024, the New England Wind project was segregated into two leases, New England Wind 1 (OCS-A 0534) and New England Wind 2 (OCS-A 0561).
Location
The New England Wind project will be located about 20 nautical miles (nm) from the southwest corner of Martha’s Vineyard, Massachusetts, and about 24 nm from Nantucket, Massachusetts.
New England Wind 1 (leased by Park City Wind, LLC) will be located 37 km off the coast of Massachusetts. It will export power via two export cables which will make landfall in the town of Barnstable, Massachusetts and will have a grid connection location of West Barnstable Station.
New England Wind 2 (leased by Commonwealth Wind, LLC) will be located 23 km off the Massachusetts coast. It will have a grid connection location of Barnstable, Massachusetts.
Project Timeline
- 2027, December: Anticipated to be Fully Commissioned
- 2026, January: Anticipated Onshore and Offshore Construction Start
- 2024, July: Construction and Operations Plan (COP) approved
- 2024, May: New England Wind segregated into New England Wind 1 (OCS-A 0534) and New England Wind 2 (OCS-A 0561)
- 2024, April: Record of Decisions (ROD) approved
- 2024, February: Final Environmental Impact Statement (FEIS) available
- 2022, December: Draft Environmental Impact Statement (DEIS) published by BOEM
- 2022, December: NMFS ESA Consultation Anticipated
- 2022, September: NMFS ESA and EFH Consultation Packages Submitted
- 2022, June: Development of Regional Impact Review Applications Filed with Cape Cod Commission (Barnstable County) and Martha’s Vineyard Commission
- 2022, April: Addendum to Construction and Operations Plan (COP) Filed
- 2021, December: Revised Construction and Operations Plan (COP) Filed
- 2021, June: Revised Construction and Operations Plan (COP) Filed
- 2021, June: NEPA Environmental Review Initiated
- 2020, July: Construction and Operations Plan (COP) Filed
- 2018, May: Offtake Conditionally Secured
- 2017, March: Site Assessment Plan (SAP) Submitted
- 2015, January: Site Exclusivity Obtained
Licensing Information
The lead permitting agency, the Bureau of Ocean Energy Management (BOEM), approved the Construction and Operations Plan (COP), Record of Decision (ROD), and Final Environmental Impact Statement (FEIS) in 2024, during which the project was segregated into two leases. Other federal agencies involved in the permitting included the U.S. Army Corps of Engineers, U.S. Environmental Protection Agency, and National Oceanic and Atmospheric Administration Fisheries (NOAA) National Marine Fisheries Service (NMFS). State agencies involved in the permitting included the Massachusetts Department of Environmental Protection, the Massachusetts Environmental Policy Act (MEPA), Massachusetts Division of Fisheries and Wildlife, Massachusetts Board of Underwater Archaeological Resources, Massachusetts Department of Public Utilities, and Massachusetts Energy Facilities Siting Board. The project name changed from Vineyard Wind South to New England Wind in 2021.
Key Environmental Issues
- 2025, June: The Wampanoag Tribe of Gay Head (Aquinnah), along with environmental groups and fishing charter businesses, filed a lawsuit against the federal agencies (March 2025: ACK for Whales filed a petition with the U.S. EPA, requesting the agency rescind the Clean Air Act permit it granted to New England Wind to construct and operate its offshore wind farm) that approved the project over concerns about the environment and marine mammals, claiming they violated multiple environmental laws when issuing a Record of Decision (ROD) for the offshore project
- 2025, March: ACK for Whales filed a petition with the U.S. EPA, requesting the agency rescind the Clean Air Act permit it granted to New England Wind to construct and operate its offshore wind farm.
- 2025, April: Barnstable-based group Save Greater Dowses Beach petitioned the EPA to conduct an additional review for the already approved project, citing concerns an expanded substation on land could harm the aquifer – the community’s source of drinking water.
- 2025, May: ACK for Whales, Green Oceans, charter fishing groups and the Wampanoag Tribe of Gay Head (Aquinnah) sued the federal government; they are asking the court to vacate agency approvals for the project.
- 2022, December: The Final Environmental Impact Statement (EIS) assessed foreseeable impacts on physical, biological, socioeconomic, and cultural resources that could result from the construction and installation (construction), operations and maintenance (operations), and conceptual decommissioning (decommissioning) of a commercial-scale offshore wind energy facility and transmission cable to shore known as the New England Wind Project.
- 2022, December: The Cumulative Historic Resources Visual Effects Assessment for the New England Wind 1 & 2 was conducted using cumulative viewshed models to help inform how the presence of wind turbine generators associated with the proposed project and other offshore wind projects would affect seven historic properties on Martha’s Vineyard and Nantucket. The assessment found that cumulative effects of the proposed project and other offshore wind projects would further adversely affect the setting of the historic properties, particularly Gay Head Lighthouse; however, the degree to which offshore wind projects would affect the significant characteristic of the undeveloped ocean view is small relative to the other aspects of the properties’ integrity that remain intact. Accordingly, development of the proposed project and other offshore wind projects in the Rhode Island/Massachusetts lease areas would not affect the integrity of any of the historic properties to the extent that it would make them ineligible for the National Register of Historic Places.