Skip to main content

OES-Environmental distributes metadata forms (questionnaires) to solicit information from developers involved in environmental monitoring around marine renewable energy project sites around the world. This page provides project descriptions, baseline assessment, post-installation monitoring, and links to available data and reports. Content is updated on an annual basis.

Paimpol-Bréhat Tidal Demonstration Project

Description

The Paimpol-Bréhat pilot project aimed to pave the way for the pre-commercialisation of tidal farms from 2017. At the initial stage of the project a prototype version of the 0.5 MW 16m diameter OpenHydro device was installed and tested in 2011. Following this successful prototype testing, in 2015 OpenHydro completed the design and manufacture of two turbines for a grid-connected demonstration project (2 x 2MW turbines, 16m diameter).

The first turbine was installed on the 20th of January 2016 and the second turbine was installed on the 29th of May 2016. The turbines were installed using a dedicated barge designed by DCNS/OpenHydro. Once the barge was stabilized, the turbines were lowered to the seabed using an innovative winch system equipped with hydraulic motors.

During 2016 OpenHydro developed and built a power conversion system as part of the turbine control centre (TCC), housed in a subsea pressure vessel enclosure and mounted on the subsea base. The TCC is a power electronics apparatus which performs the dual functions of controlling the turbine to achieve optimum power output and converting the electrical output of the turbine to grid compliant power (however, these devices were never grid connected in the end).

In April 2019, testing with another tidal turbine began at this test site. The HQ-OCEAN tidal turbine designed by the French start-up HydroQuest and built by CMN was immersed to a depth of 35 m. By June 2019, this device had delivered its first kilowatt hour of electricity to the grid. The testing lasted until December 2021 upon which the device was retrieved from its place on the seabed. 

OpenHydro released video footage of the installation of the first device: https://www.youtube.com/watch?v=Du7Jqscu3LE

Onshore Infrastructure: The substation that fed the electricity to the French grid is located close to the Arcouest Peninsula in Ploubazlanec.

Vessel Spread: Specifically designed catamaran barge (Triskell), a tug (Penfret) and a support boat.

Location

The project was located 16km off the coast of Brittany, France in water depths of 35m. 

Project Progress

In January 2017 it was reported that the two turbines would need to be removed to replace a faulty part which prevented the system from operating correctly. It was discovered that corrosion of bolts and fasteners was the cause of the problem.

The first and second turbines were retrieved in April and July 2017 respectively for replacement of components that threatened the turbine’s resistance to corrosion. These turbines were never redeployed and the project was subsequently cancelled by EDF in 2018.

In April 2019 the HydroQuest turbine was installed. The HydroQuest turbine was then retrieved December 2021.

Key Environmental Issues

Key environmental issues include those relevant to other tidal stream developments such as:

  • Noise impacts during construction and operation
  • Disturbance to benthic habitats
  • Potential for collision with turbine blades 

Additionally, the recommendations of the Trégor-Goëlo SMVM sea development plan include:

  • Importance of Maintaining Water Quality
  • Ecological interest of the territory
  • Risks associated with the evolution of the coastline
  • The many dynamic activities and uses that exert strong pressure on environments and competition for limited space.