Description
Minesto have developed a tidal stream energy device known as a Deep Green Utility (DGU) unit. The device resembles an underwater kite made up of a wing with a small turbine attached to the underside, tethered to a foundation fixed to the seabed. The device can also be attached to a barge or similar structure and operate in an “upside down” mode. The 0.5 MW unit (DG500) deployed between July and November 2018 was attached to a self-contained Micro Grid System (MGS) buoy, which handled and analysed electricity generated.
The DGU unit moves through the water column in a figure-of-eight, sweeping an area of approximately 100-140 m wide and taking advantage of hydrodynamic lift created by the wing as the current flows past. This allows the device to operate in areas of relatively low current velocity. The DG500 unit is 12 m (wing span) by 3.3 m, weighs between 10 and 16 tonnes and has a generating capacity of 0.5 MW.
The Holyhead Deep low-flow tidal stream project aims to put Minesto on track for commercialisation of their Deep Green technology. Developing Holyhead Deep into a grid-connected commercial tidal energy array will be carried out in phases. In Phase 1 a single non-grid connected 0.5 MW Deep Green demonstrator device (DG500) was installed at the site, the purpose of which was to prove functionality and power production performance. Commissioning of the DG500 demonstrator was initiated in June 2018 and completed in November 2018. The DG500 unit will be redeployed for further sea trials in summer 2019.
Following successful deployment and testing of a single DG500, Minesto’s ambition is to install further Deep Green devices in phases, gradually expanding the site to a commercial demonstration array of up to 10MW installed capacity. In the first instance term, in addition to further sea trials of the DG500 unit, Minesto plan to install and operate an addition uprated (at least 0.75 MW) DGU.
Minesto’s long term plan is to further expand the commercial roll-out of its Deep Green technology in Holyhead Deep by taking steps to increase the planned installed capacity of the tidal energy array to 80 MW. Minesto intends to develop the Holyhead Deep site in phases as part of a deploy-and-monitor approach. This gradual expansion would see the Deep Green technology progressing from demonstrator to full industrial roll-out in North Wales.
Minesto has been awarded a new patent for its Deep Green technology to enhance its efficiency and scalability. In addition to project developments, Minesto signed an MoU with Schneider Electric to enhance grid compatibility testing for future large-scale deployments of the Deep Green technology.
Export Cables: The electricity produced by the DG500 is transmitted directly to a self-contained Micro Grid System buoy via a subsea umbilical cable where it is monitored and then dissipated. Electricity produced by the DGU will be transmitted via a subsea umbilical cable running from the foundation to the surface MGS buoy.
Vessel Spread:
|
Activity |
Vessel Type |
Indicative Operating Period |
|
Installation |
||
|
Deploying pin piled tripod, monopile, mud mat or GBS. |
DP vessel or underslung barge (depending |
Maximum of five days. |
|
Installation of MGS buoy |
Anchor handler tug or multicat. |
Approximately 1 week. |
|
Transport of MGS buoy to site. |
Tug(s). |
1 day per transfer, but multiple transfers expected. |
|
Transport DGU unit to site. |
LARS support vessel designed specifically |
1 day per transfer, but multiple transfers expected. Could |
|
Deployment of an ROV to attach tether to foundation, if not handled from barge deck). |
Support vessel with ROV capabilities. |
Less than 1 week. May also be required intermittently |
|
Operation |
||
|
Field testing and calibration of DGU unit and hosting of electricity meter. |
Barge (or similar such surface platform). |
Throughout the 5 year testing period, although |
|
Retrieval, deployment and routine maintenance of DGU unit. |
LARS support vessel designed specifically |
Throughout the 5 year testing period. |
|
Unplanned maintenance of DGU power plant. |
Service vessel, occasional requirement |
Approximately 6 days per year. |
Location
The deployment site is located in the southern corner of Holyhead Deep, off the northwest coast of Wales. The area was carefully selected to maintain separation from shipping lanes and to minimise the impact on other sea users.
Licensing Information
In April 2017 Minesto received a Marine Licence (ref. ORML1618) under the Marine Works (Environmental Impact Assessment) Regulations 2007, for the initial 0.5 MW phase of their Holyhead Deep project. This was approved by the Natural Resources Wales Marine Licencing Team on behalf of the Welsh Ministers. The EIA Consent Decision can be viewed here.
The project has also secured additional funding through the Swedish Energy Agency to support the commercialization of the Deep Green technology.
Licencing Conditions:
The following project-specific conditions relevant to environmental monitoring and management were stated within the Marine Licence (ref. ORML1618):
8.3 The Licence Holder must submit an Environmental Monitoring Strategy (EMS) to NRW acting on behalf of the Licensing Authority for written approval at least 8 weeks prior to commencement of the works. No works may be undertaken prior to written agreement from NRW acting on behalf of the Licensing Authority.
The EMS must include, but may not be limited to:
- Underwater noise monitoring;
- Scour monitoring; and;
- Marine mammal monitoring.
The Licence Holder must submit an Adaptive Environment Management Plan (AEMP) to NRW acting on behalf of the Licensing Authority for written approval at least 8 weeks prior to commencement of the works. No works may be undertaken prior to written agreement from NRW acting on behalf of the Licensing Authority.
The AEMP must include, but may not be limited to:
- All mitigation measures outlined in the Environmental Statement;
- Adaptive management
- Operational management and mitigation; and
- Marine mammal mitigation protocol.
Project Progress
In November 2013 Minesto submitted a scoping report to UK consenting authorities Marine Management Organisation (MMO) and Natural Resources Wales (NRW), asking for their scoping opinion for development of a 1.5 MW site in Holyhead Deep.
In spring 2018, Minesto installed and commissioned the DG500 site infrastructure consisting of the seabed foundation, tether, umbilical and a buoy containing a microgrid system (MGS). The MGS provided auxiliary power and communications to the DG500 device
In May 2018 a micro grid system (MGS) buoy was installed, which provided auxiliary power and communications to the DG500 device, as well as acting as a floating micro grid system to facilitate grid compatibility testing by handling and analysis electricity generated by the DG500 device.
Minesto initiated commissioning of its DG500 demonstrator device in June 2018, which consisted of two main phases. The first stage comprised a series of tests including verification of launch and recovery procedures, testing of each function of the control system, and finally operation of the DG500 in full figure-of-eight trajectories. The second stage involved electricity generation.
At the end of August 2018 Minesto unveiled its DG500 marine energy kite device after verifying the functionality of the Deep Green technology at utility scale. Minesto resumed further testing before the second commissioning phase to verify the power take-off system and electricity generation. The device generated electricity for the first time in early October.
The offshore commissioning and test programme of the DG500 device completed in November 2018.
In May 2019 the Welsh European Funding Office awarded 14.9 million of EU funding for the next phase of Minesto’s Holyhead Deep site. The investment will include:
- Continued site development and operations at Minesto’s Holyhead Deep site
- Enhancement of Minesto’s utility-scale product range;
- Installation and operation of an additional , uprated (at least 50% higher than the current 0.5MW system) unit in Holyhead Deep;
- Strengthened manufacturing and assembling capability;
- Securing permits and consents for expanding the Holyhead Deep site towards a commercial 80MW tidal energy farm; and
- Design of subsea infrastructure for the 80MW site development.
Minesto is seeking to submit consent applications and Environmental Statement for the 80MW later in 2019. The 0.5 MW non grid connected DG500 device was redeployed in August 2019 in Holyhead Deep site offshore North Wales, along with a hydrophone array to monitor cetacean activity around the device. In late 2021, the Swedish Energy Agency has awarded Minesto a SEK 5.8 million grant to the ongoing commercialisation of the Deep Green technology.
As of May 2025, Minesto continues testing, including a commitment to increase the installed capacity and expand the project with new units and collaborations.
Key Environmental Issues
The following potential impacts were deemed to be potentially significant during the EIA process: Collision risk for marine mammals and diving birds. Possible impacts on bottlenose dolphin were a particular concern, given the small population size of this species in Welsh inshore waters.
Mitigation Measures: The following key mitigation and best practice measures to be applied are outlined in the Environmental Statement:
- All vessels associated with Project operations will comply with all relevant guidance (including IMO guidelines) regarding ballast water and transfer of Marine non-native species (MNNS)
- Best practice measures to reduce the risk of and impact from vessel hydrocarbon and chemical spills (see ES for details). The mitigation measure detailed in the Hydrocarbon and chemical spills and Shipping and navigation sections of this table will minimise the risk and uncertainty associated with accidental spills to ensure that Project activities do not significantly impact the marine mammals in the Project area or wider region.
- Development of an Environmental Monitoring Strategy.