Contents
Wind Project Site
(login for email address)
Details
Description
RWE Renewables’ Rhyl Flats Offshore Wind Farm is comprised of 25 wind turbines and has a 90 MW capacity which can power over 70,000 average UK households (equivalent to cutting 1.7 million tonnes of CO2 emissions per year). The wind farm occupies an area of approximately 10 square kilometres.
Rhyl Flats is operated by RWE and is owned by a consortium of RWE (50.1%), Green Investment Group (24.95%) and Greencoat (24.95%). The project was initially developed by Celtic Offshore Wind Limited (COWL) as part of the UK's Round 1 offshore wind farm programme.
Location
Rhyl Flats Offshore Wind Farm is located in Liverpool Bay, roughly 8 km off the North Wales coast at the eastern end of the Constable Bank.
Project Timeline
- 2009: Fully Commissioned
- December 2009: Generating Power
- July 2008: Foundation Piles Installation Completion and Offshore Cabling Installation Start
- April 2008: Foundation Piles Installation Start
- 2008: Onshore Construction Start
- July 2007: Offshore Foundation Construction Start
- 2006: Start of Site Investigations
- December 2002: RWE purchased the Rhyl Flats project from COWL
- 2002: Celtic Offshore Wind Limited (COWL) received full consents
- 2002: Offtake Conditionally Secured
- 2001: Site Exclusivity Granted
Key Environmental Issues
Per the Non-Technical Summary of the Rhyl Flats Environmental Impact Assessment, potential impacts to ecology, marine mammals, fish, and ornithology were minimized through the adoption of mitigation measures during the design, construction, and operation of the project.
Environmental Papers and Reports
- Enhanced bed shear stress and mixing in the tidal wake of an offshore wind turbine monopile Austin et al. 2025
- Understanding commercial fish space use around Marine Renewable Energy sites: novel acoustic array-based fish tracking and monitoring at Wave Hub, Cornwall Sims and Cotterell 2013
- High Resolution Video Survey of Seabirds and Mammals in the Rhyl Flats Area Hexter 2009
- Rhyl Flats Offshore Wind Farm Ltd. Project Environmental Management Plan npower renewables 2008
- Rhyl Flats Wind Farm: Environmental Management Plan (Version 2.2) npower renewables 2008
- Rhyl Flats Offshore Wind Farm Monitoring Statement (Version 1.4) npower renewables 2007
- Rhyl Flats Offshore Wind Farm Benthic Trawl Survey 2006 Monitoring Report Centre for Marine and Coastal Studies Ltd (CMACS) 2007
- Rhyl Flats Offshore Wind Farm Benthic Grab Survey 2006 Monitoring Report Centre for Marine and Coastal Studies Ltd (CMACS) 2007
- Rhyl Flats Offshore Wind Farm Baseline Report Fish & Fisheries Lockwood 2007
- Annual FEPA Monitoring Report (2005-6) Rhyl Flats Offshore Wind Farm Interim Ornithology Chapter Gill et al. 2007
- Rhyl Flats Offshore Wind Farm Development: Seabed Comparison npower renewables 2006
- Rhyl Flats Offshore Wind Farm Grab Survey Field Report Centre for Marine and Coastal Studies Ltd (CMACS) 2005
- Rhyl Flats Offshore Wind Farm Beam Trawl Survey Report Centre for Marine and Coastal Studies Ltd (CMACS) 2005
- Rhyl Flats Environmental Impact Assessment Anatec et al. 2002
Additional Rhyl Flats data can be found on the Marine Data Exchange.
Environmental Monitoring: Rhyl Flats
| Phase | Stressor & Receptor | Design and Methods | Results | Publications | Data |
|---|---|---|---|---|---|
| Baseline | Birds | Aerial Video Surveys
A HiDef aerial video survey was carried out over two days on the 5th and 8th of April 2009. The aim of this trial was to demonstrate the ability to identify red throated divers from video data. |
Complete
A total of 15 red-throated divers were identified giving a population estimate of 75. |
Hexter 2009 | |
| Baseline | Birds | Ornithological Surveys
Ornithological survey data was collected from August 2005 to November 2006. Aerial and boat-based surveys were conducted. |
Complete
Unidentified divers, cormorant, auks, common scoters, and kittiwake were among the most observed species. |
Gill et al. 2007 | Annual FEPA Monitoring Report (2005-6) Rhyl Flats Offshore Wind Farm Interim Ornithology Chapter |
| Baseline | Birds | Boat and Aerial Surveys, Data Review
Boat surveys were undertaken from January to March 2002 at ten sample point locations in the wind farm site. Aerial surveys were conducted in December 2001 and January 2002. Existing relevant published information was reviewed. |
Complete
Boat surveys recorded scoter movement during the day. Aerial surveys were a part of a common scoter survey. |
Anatec et al. 2002 | No data publicly available. |
| Baseline | Fish, Physical Environment | Beam Trawl Surveys
A beam trawl survey was undertaken during September 2006. The beam trawl survey was conducted between the 5th and the 7th of September 2006. A digital photograph of each sample was taken before any sorting or identification of organisms took place. |
Complete
954 fish from 23 fish taxa were recorded. The largest number of individuals were recorded at sites 12 and 13 on the planned cable route and site 2 located in the northwest of the wind farm area. 1,014 fish from 15 species were recorded. The largest number of individuals recorded along the proposed cable route. Relatively high numbers of individuals were also observed at sites to the south of the array. |
Centre for Marine and Coastal Studies Ltd (CMACS) 2007, Centre for Marine and Coastal Studies Ltd (CMACS) 2005 | 2006, CMACS, Rhyl Flats Offshore Wind Farm, Beam Trawl Survey 2005, CMACS, Rhyl Flats Offshore Wind Farm, Beam Trawl Survey |
| Baseline | Physical Environment | Grab Surveys and Sediment Analyses
A benthic grab survey was conducted in 2006 at twenty-nine sites in the Rhyl Flats Offshore Wind Farm project area. The results were compared to the findings of the previous 2005 monitoring survey. A grab sampling survey was undertaken during October 2005 during the pre-construction phase of the Rhyl Flats Offshore Wind Farm project. These surveys will be repeated annually as part of the proposed monitoring. |
Complete
Of the twenty-nine designated sampling sites, twenty-six were successfully sampled in 25 grab stations were successfully sampled retrieving 3 faunal and 3 PSA samples from each. |
Centre for Marine and Coastal Studies Ltd (CMACS) 2007, Centre for Marine and Coastal Studies Ltd (CMACS) 2005 | 2006, CMACS, Rhyl Flats Offshore Wind Farm, Benthic Grab Survey |
| Operations | Changes in Flow Physical Environment |
Monopile wake and turbulence monitoring
An acoustic Doppler current profiler measured currents and turbulence approximately 41 m from a turbine monopile during September 2022. Measurements compared upstream conditions with the downstream turbine wake. |
Complete
The wake increased turbulence throughout the water column. The estimated seabed drag coefficient approximately doubled, and vertical mixing increased substantially. |
Austin et al. 2025 | Austin, M. (2024). ECOWIND-ACCELERATE Rhyl Flats ADCP 2022 [Dataset]. Zenodo. https://doi.org/10.5281/zenodo.12530957 |