Description
At 1.32 GW, Hornsea 2 will overtook Hornsea 1 as the world’s biggest offshore wind farm when it came online in August 2022. The farm comprises 165 Siemens Gamesa SG 8.0-167 DD turbines and is 100% owned by Ørsted. The farm covers an offshore area of 462km² and is located directly next to Hornsea 1 in the North Sea off the coast Grimsby, England.
For more information on the Hornsea projects, check out this 60 minutes video! Or view Ørsted's Hornsea 2 Photography Exhibition.
Location
Hornsea 2 is located 89 km (55.302 miles) off the Yorkshire coast in the North Sea, adjacent to Hornsea 1. Hornsea 2 is located 55 miles east of the Port of Grimsby. The cable makes landfall at Lincolnshire’s Horseshoe Point beach. The farm is operated and maintained from Ørsted's East Coast Hub in Grimsby which supports a workforce of over 600 people.
Project Timeline
- August 2022: Hornsea Two became fully operational
- October 2020: Offshore construction began
- April 2019: Onshore cable installation work began
- July 2018: Construction of onshore substation commenced
- April 2018: Site investigations offshore and enabling works on the onshore substation commenced
- September 2017: Contract for Difference awarded to the Project and Final Investment Decision made
- August 2016: Secretary of State grants Development Consent Order
- October 2012: Environmental Impact Assessment Scoping Report
Licensing Information
- 2020: Department for Business, Energy & Industrial Strategy (BEIS); Safety Zone Permit
- 2019: Department for Business, Energy & Industrial Strategy (BEIS); Decommissioning Programme
- 2018: Department for Business, Energy & Industrial Strategy (BEIS); Development Consent Order (DCO) Amendment
- 2016: Department for Business, Energy & Industrial Strategy (BEIS); Development Consent Order (DCO)
- 2016: Marine Management Organisation (MMO), Deemed Marine Licences (DML)
Key Environmental Issues
Key species known to occur in the project area are harbor porpoises, white-beaked dolphins, minke whales, as well as grey and harbor seals. Prior to any construction activities taking place, dedicated Marine Mammal Observers (MMOs) monitored the area for any animals that could be affected by the noise produced from pile driving. Monitoring took place from DEME’s jack-up vessels during the installation of the monopiles, as well as Heerema’s semisubmersible crane vessel Sleipnir during the construction of the two offshore substations. In addition to visual monitoring to ensure marine mammals are not within close proximity to piling operations, acoustic deterrent devices (ADDs) were used to deter animals from the area to protect them from harmful levels of noise.