Skip to main content

Partnering with WREN, questionnaires are sent to offshore wind energy developers around the world who are involved in environmental monitoring. This page provides contextual project information and highlights environmental monitoring, providing links to available data and reports. Content is updated annually.

Saint-Brieuc Offshore Wind Farm

Description

The Saint-Brieuc offshore wind farm is the second large-scale offshore wind project in France and the first in Brittany and the western English Channel. The wind farm was fully commissioned in 2024 and has a total installed capacity of 496 megawatts (MW) and a production capacity of 1,820 gigawatt hours per year. It was financed by Iberdrola for roughly 2.4 billion euros and developed and operated by subsidiary, Ailes Marines.  

The development and construction of the wind farm and associated facilities mobilized more than 1,700 jobs in France, including more than 500 in Brittany. The jackets and piles were built and assembled by Navantia-Windar in Spain, then transported by sea to Brest. The assembly of the towers was carried out on the new polder at the Port of Brest, which was completed in 2022. Van Oord was responsible for the transport and installation of the jackets and offshore substation with its high-seas support vessel, Aeolus. The offshore substation was manufactured in Belgium by a joint venture between Smulder and Equans. GE Renewable Energy Grid Solutions supplied and installed the major electrical equipment for the substation. The undersea cabling connection systems were provided by Prysmian Group, which installed and commissioned 90 km of high-voltage 66 kV AC connection cables and three hubs with XLPE insulation. Réseau de Transport d’Électricité (RTE) oversees operations and maintenance of the cables from the substation to the grid connection. 

Location

The Saint-Brieuc offshore wind farm covers an area of 75 km2 in the Saint-Brieuc Bay of the English Channel in Brittany, France. It is located 16 km from the nearest coast on a coarse sand and gravel seafloor, in water depths between 29-42 m. The wind farm is composed of 62 turbines arranged in 7 rows of 3 to 14 turbines, with 1,000 m between each turbine and 1,400 m between each row. An offshore substation is located at the center of the wind farm. Cable landfall occurs at the Caroual Beach, near Erquy, with connection to the grid at the Doberie substation at Hénansal. An operation and maintenance centre in located nearby at Binic-Étables-sur-Mer. 

Project Timeline

  • May 2024: Fully operational and commissioned.
  • December 2023: Complete installation of the 62 turbines, on schedule.
  • July 2023: First electrical production.
  • May 2023: Installation of the first turbine.
  • July 2022: Complete installation of the offshore substation.
  • June 2021: Completion of cable landfall construction.
  • May 2021: At-sea construction activities started in the northern part of the farm.
  • 2020: Completion of the pre-construction technical and environmental analyses.
  • 2017: Final decisions from French government and relevant prefectures awarded.
  • 2016: Public consultation conducted.
  • 2012: Ailes Marines awarded the Saint-Brieuc offshore wind farm project. 

Licensing Information

Once awarded in 2012, construction and operation of the wind farm relied on securing relevant authorizations under articles L.214-1 and those that follow (a.k.a. “water law”) and L.2124-3 and those that follow of the General Code of the Property of Public Persons (a.k.a. “grant of use of the maritime domain”). Articles R.122-1 and following of the Code of the Environment list the requirements for the impact study of the operating wind farm, and article L.122-3-II of the Code of the Environment lists those for the impact study of the construction activities. In April 2017, the project received the final authorizations from the French administration (Côtes-d’Armor prefecture). Several monitoring requirements, mitigation measures, and compensation measures were required as part of the authorization. 

Key Environmental Issues

Environmental studies began in 2012 and continued during construction and operations. Several key environmental issues have guided the implementation of these studies: impacts to marine mammals, birds, and bats; effects on benthic communities and fisheries (including bivalves and crustaceans); and changes in water quality (e.g., sediment, chemical releases). These studies cover four aspects: compensatory measures, environmental monitoring, mitigation measures, and research studies.  

  • Compensatory measures have consisted of 1) improving the protection of marine mammals in a large area from the Bay of Lannion in the west to the coastline of Normandy in the east; 2) improving nesting conditions for seabirds on the Cape Fréhel by lowering the local predatory pressure by black crows and ravens; and 3) enabling the return of nesting birds to Tomé Island by completely eradicating the invasive American mink from the island and stopping the species from settling on the nearby Seven Island Archipelago.
  • Environmental monitoring measures have focused on 1) seabird species around the Bay of Saint-Brieuc to improve knowledge on nesting populations and rearing habitats; 2) marine mammals and seabirds at sea to assess any impact from wind farm construction and operation; 3) migratory birds (including seabirds) during spring and fall migrations; 4) fishery resources, including bivalves, fish, crustaceans, and cuttlefish, to determine any potential impacts of construction and operation on stocks; and 5) impacts to benthic species, sediment, and water quality from construction activities and antifouling sacrificial anodes.
  • Mitigation measures have consisted of using a different port as initially selected for staging all construction activities in order to highly decrease any potential interaction with Balearic shearwater during vessel transits to and from the wind farm.
  • Research studies have so far focused on 1) investigating in laboratory setups and in the field how underwater noise emissions may affect fishery resources such as scallop, other fished bivalve species, lobster, and cuttlefish; and 2) modelling the transport and accumulation of resuspended sediments during drilling and trenching, and the exposure of scallops to suspended matters.