Annex IV distributes metadata forms (questionnaires) to solicit information from developers involved in environmental monitoring around marine renewable energy project sites around the world. This page provides project descriptions, baseline assessment, post-installation monitoring, and links to available data and reports. Content is updated on an annual basis.

Haishan Tidal Power Plant

Project Site Annex IV

Title: Haishan Tidal Power Plant
Developer:
Start Date:
December 01, 1975
Country:
Technology Type:
Info Updated:
November 14, 2017
Project Status: 
Device in operation
Project Scale: 
Commercial
Installed Capacity: 
0.25 MW
Description: 

The Haishan TPP is noteworthy as it is the only linked-basins plant in existence in the world a plant featuring a high and a low-basin with the power plant in between these two basins, generating energy from water flowing from the high into the low-basin generating the power in only one direction. The inlet gate was set up at one projecting beach on a sea island. The station was placed at the link-up of the high and low reservoirs. The water outlet gate was set up at the southeast of the low reservoir. The area of the upper reservoir is 22.9 hectares and 0.8 hectares at lower reservoir. The average tidal range is 4.91m. The plant serves an isolated community of 760 families. This unit operated continuously. The energy was used partly to pump fresh water for domestic and irrigation use into the community reservoir.

Location: 

Maoyan Island, Zhejiang Provice, China.

Process Status: 

This power station was completed and put to use in 1972. The plant was designed for two 75kW units of which only one was installed and commissioned in 1975. The plant has since been upgraded to an installed capacity of 0.25 MW, producing 0.34GWh per year.

 

Since the sediment transport processes are changing, the advantage of the physical environment of the tidal power station has been changed.

Key Environmental Issues: 

The mud and sand conditions of this power station are similar to that of Jiangxia power station. Yet its inlet was placed at the shallow shoal on projecting shore, where the two streams converge, carrying more sand and mud, more easily to be silted up. So when this power station is in operation, its sedimentation is so serious that it has silted up 63cm during eight years. One would expect however that, like most other seas, the Yellow and East China Seas are host to migratory fish species which need access to coastal bays, estuaries and rivers for their feeding and procreation. To what extent this has been taken into account by China's TPP engineering community is not clear.

Haishan Tidal Power Plant is located in China.

Baseline Assessment: Haishan Tidal Power Plant

ReceptorStudy Description Design and Methods Results Status
  • Marine Uses
N/A

Practice

The stable environment of the reservoir is suitable for algae, shellfish and shrimp growth.This formed a good condition for aquaculture,conducive to the comprehensive utilization of reservoir.