Skip to main content

Partnering with WREN, questionnaires are sent to offshore wind energy developers around the world who are involved in environmental monitoring. This page provides contextual project information and highlights environmental monitoring, providing links to available data and reports. Content is updated annually.

Horns Rev 1

Description

Horns Rev 1, built by Danish energy company Elsam (later DONG, now Ørsted), was the first large-scale offshore wind farm in the world. Today it is jointly owned by Vattenfall (60%) and Ørsted (40%). Its capacity of 160 MW was four times that of the previous largest, the Middelgrunden at 40 MW. Horns Rev 1 is the first phase of three wind farm projects, with Horns Rev 1 coming online in 2002, Horns Rev 2 in 2009, and Horns Rev 3 in 2019. Horns Rev 1 was the first offshore wind farm in the North Sea, the first to use the monopile foundation type, and the first to have its transformer on an adjacent platform rather than onshore. Horns Rev 1 was also the first offshore wind farm to use steel monopile foundations 18 km from the coastline, and the first to have its own designated offshore substation. Technologies used for the first time at Horns Rev 1 have since become industry standard. Ørsted has a long-standing R&D partnership program with universities and research institutions worldwide and has been sharing big data from its Horns Rev 1 with selected universities. 

Location

The Horns Rev 1 wind farm is in the North Sea about 14 to 20 km offshore from the Danish coastline, specifically about 20km west off Blåvandshuk on the west coast of Jutland. The power generated passes to a transformer platform on the fringe of the offshore wind farm, where the voltage is transformed up to 150 kV before the electricity is taken to the shore through a 21-km submarine cable to Hvidbjerg Strand. The submarine cable, manufactured in Norway, is the first plastic-insulated 150 kV cable in the world. With a diameter of 19.2 cm, it is also the thickest submarine cable ever made.  The Port of Esbjerg is the nearest port to Horns Rev 1. 

Project Timeline

  • 2005: Vattenfall acquired a 60% stake in the wind farm
  • 11 Dec 2002: Horns Rev I was fully commissioned
  • 29 Jul 2002: First turbine begins generating power
  • 01 Mar 2002: Horns Rev I offshore construction starts
  • 29 Mar 2001: Consent authorized
  • 15 June 1999: Consent application submitted 

Licensing Information

The Horns Rev I offshore wind farm project originated in February 1998 when the Danish Minister of Environment and Energy ordered its establishment. By March 29, 2001, the project received final approval from the Danish Energy Agency, marking a significant milestone in its regulatory development. 

Key Environmental Issues

Between 1999 and 2006, a comprehensive environmental monitoring programme was carried out to evaluate the environmental impact of the Horns Rev and the Nysted Offshore Wind Farms, two of the biggest farms in the world at the time. Between 1999 and 2001, as part of the Environmental Impact Assessments (EIAs) and as the basis for the environmental monitoring  programme, baseline studies were undertaken to establish a reference for later analysis (Danish Energy Agency).  

The studies and analyses in the environmental monitoring programme dealt with:

  • Benthic fauna and vegetation: Studies of bottom fauna and vegetation, including the food basis for fish, with particular focus on the introduction of a hard bottom habitats, e.g. the turbine foundation and scour protection.
  • Fish: Studies of the distribution of fish around the wind turbines and the scour protection and the impact of electromagnetic fields on fish.  
  • Marine mammals: Studies of the behaviour of harbour porpoises and seals in and near the wind farm areas.  
  • Birds: Studies of resting, foraging and moulting birds, including modelling of collision risks and monitoring of bird collisions with wind turbines.
  • Attitudes: Sociological and environmental economic studies of people’s attitudes towards the wind farms.

As a follow-up to the environmental monitoring programme, a new programme ran from 2009- 2012 that focused on fish, harbour porpoises, birds and various cumulative effects. The final results of this follow-up can be found in Danish Energy Agency (2013). Additional information can be found here