Skip to main content

Project Environmental Monitoring Plan: Kincardine Offshore WindFarm Project March 2025

Abstract

This document has been created to satisfy Condition 22 of the Section 36 Consent originally issued 
by Marine Scotland Licensing Operations Team (MS-LOT, now MD-LOT) to Kincardine Offshore Wind 
Ltd (KOWL) for the Kincardine Offshore Windfarm (the Project). 


Condition 22 requires the production of a Project Environmental Monitoring Plan (PEMP). The overall 
aim of the PEMP is to outline and define the approach KOWL, its survey contractors and advisors will 
take with respect to the environmental monitoring of the Project required under the consent conditions. 


The PEMP is designed to provide guidance to those involved in the Project, on the monitoring of 
potential environmental impacts associated with the installation, post-construction and operational 
phases of the wind farm. 


This iteration of the PEMP (revision C10) has been adapted from that originally prepared for the initial 
stages of the Project, in order to build upon learnings during the data collected during operation of the 
2MW turbine and to refine the monitoring objectives and methodologies subsequent to the installation 
and operation of five 9.5MW turbines at the site. 


The document is structured into 8 main sections plus Appendices: 


Section 1 Introduction: This section sets out the purpose, structure, scope of the document as 
well as the approach to updating it, and compliance with consent conditions 


Section 2 Project Overview: This section summarises the main features of the Kincardine 
project, turbine locations, its principal and currently installed components, the project design life, and 
an overview of the construction programme. 


Section 3 Consent Conditions: This section describes the main consent conditions for the 
Kincardine project, and highlights where each consent condition is addressed in the relevant sections 
of this document. 


Section 4 Birds Monitoring Plan: This section focuses on the monitoring plan for birds at the 
site. It starts with a summary of meetings held to-date with stakeholders, and the key outcomes and 
agreements from each of these meetings. The overarching approach to bird monitoring is summarised, 
and the various objectives of the bird monitoring studies and methods to be employed at the site are 
then discussed in turn. The reporting requirements are described, and this is followed by a summary 
table of the main activities that have been carried out and are planned for bird monitoring at the site. 


Section 5 Marine Mammals Monitoring Plan: This section focuses on the monitoring plan for 
marine mammals at the site. It starts with a summary of meetings held to-date with stakeholders, and 
the resultant key outcomes and agreements. The overarching approach to marine mammal monitoring 
is summarised, and the various objectives of the marine mammal monitoring studies and methods to 
be employed at the site are then discussed in turn, along with details of activities carried out to-date. 
The reporting requirements are described, and this is followed by a summary of the activities that have 
been carried out and are planned for monitoring the potential effects upon marine mammals at the 
site. 


Section 6 Diadromous Fish Monitoring Plan: This section focuses on the monitoring plan for 
diadromous fish at the site. It starts with a summary of meetings held to-date with stakeholders, and 
the key outcomes and agreements from each of these meetings. The overarching approach to 
diadromous fish monitoring is summarised, and the various objectives of these monitoring studies and 
methods to be employed at the site are discussed. The reporting requirements are described, and this 
is followed by a summary of the main activities that are currently being carried out. 

Section 7 Unexploded Ordnance (UXO) Clearance: This section describes the approaches that KOWL will undertake and references the guidance documents that KOWL will consult, should any UXO clearance activities be required at the site in the future.

Finally, Section 8 presents an overall summary of the key monitoring activities and recent reporting outputs at Kincardine as of March 2025.

Appendix A presents technical details and specifications of the DTBird video camera systems that are installed at the site to monitor bird collisions.

Appendix B contains details of key contractors and advisors.

Appendix C illustrates the field layout and locations of each WTG at the KOWL site.
 

This document is related to the Kincardine Offshore Wind Farm Project Site.