Description
The Fundy Ocean Research Centre for Energy (FORCE) was established in 2009 as Canada’s leading test centre for tidal energy technology. FORCE is a non-profit grid-connected test facility in the Minas Passage, Bay of Fundy, intended to allow developers, regulators, scientists, and academics to study and demonstrate the performance of in-stream tidal energy turbines and their interactions with the environment. The FORCE site consists of five subsea berths for tidal stream energy conversion devices, subsea power cables that can enable connection of turbines to land-based infrastructure, a subsea data cable, an onshore transformer substation, and a shore-based visitor centre.
Location
FORCE’s test site is in the Minas Passage area of the Bay of Fundy near Black Rock, 10 km west of Parrsboro, Nova Scotia. Minas Passage, only 5 km wide and bordered by basalt cliffs, is the entrance to Minas Basin, the region of the world’s highest tides. FORCE is located in Mi’kma’ki, the ancestral and unceded territory of the Mi’kmaq, covered by the “Treaties of Peace and Friendship” which Mi’kmaq and Wolastoqiyik (Maliseet) People first signed with the British Crown in 1725. Mi’kmaw Peoples have lived on and cared for this land for over 13,500 years.
At mid-tide, the current in Minas Passage is about 4 cubic km per hour. About 160 billion tonnes of water flows through the Bay of Fundy each tidal cycle, equal to four times the estimated flow of all the freshwater rivers in the world combined. With the incoming tide, approximately 14 billion tonnes of sea water flows through Minas Passage into Minas Basin, and central Nova Scotia tilts slightly under the immense load.
Licensing Information
The complete Environmental Assessment Registration Document for FORCE (Registered on June 17, 2009 under the Nova Scotia Environment Act), including the Terms and Conditions of Approval (including addenda from 2010 and 2015) can be viewed here. The complete Environmental Assessment Registration Document for FORCE (Registered on June 17, 2009 under the Nova Scotia Environment Act), including the Terms and Conditions of Approval (including addenda from 2010 and 2015) can be viewed here. The conditions of its EA approval provide for comprehensive, ongoing, and adaptive environmental management. The EA approval has been amended since it was issued to accommodate changes in technologies and inclusion of more berths to facilitate provincial demonstration goals.
FORCE also has a Crown land lease from the Province of Nova Scotia, which allows it to conduct activities at its demonstration site. Berth holders at the FORCE site are selected by the Nova Scotia Department of Energy and Mines.
Each berth holder is responsible for obtaining all permits and approvals for their individual project. This includes authorizations and/or reviews from Fisheries and Oceans Canada, Transport Canada, and a review of its environmental effects monitoring program by the Nova Scotia Department of Environment.
Project Progress
As Canada’s leading test centre for tidal stream energy technology, FORCE has worked to advance marine research in the Bay of Fundy and beyond since 2009 with the first deployment of an OpenHydro turbine. In 2014, FORCE installed four subsea power cables, which will enable berth holders to connect to the Nova Scotia electrical grid.
Current berth holders include:
- Berth A: Eauclaire Tidal Limited Partnership
- Berth B: Rio Fundo Operations Canada Limited
- Berth C: Sustainable Marine Energy Canada
- Berth D: Big Moon Power Canada
- Berth E: Haligonia Tidal Energy Limited
FORCE provides common infrastructure and permits, including:
- Subsea power cabling: four 34.5kV cables installed, totalling 11km and 64MW capacity
- Substation: 30MW transformer and turbine control bays
- Grid connection: 10km of 69kV transmission line, connecting FORCE substation to provincial power grid via existing Parrsboro substation
- Provincial and federal approvals, including Environmental Assessment and Generator Interconnection Agreements
- FORCE-managed on-site work permitting
In addition, FORCE has implemented several key programs:
- Fundy Advanced Sensor Technology (FAST) Program, which consists of onshore and offshore assets to support research and development and to advance efforts to monitor and characterize the FORCE site.
- Environmental Effects Monitoring Program (EEMP), which has been in place since 2009 to better understand the natural environment of the Minas Passage and the potential effects of turbines as related to fish, seabirds, marine mammals, lobster, marine noise, benthic habitat and other variables. All documents are available online: fundyforce.ca/document-collection
- Risk Assessment Program for Tidal Stream Energy (RAP), which is intended to create a detailed, credible assessment tool to gauge the probability that fish will encounter a tidal device by combining biological data and physical oceanographic data.
Key Environmental Issues
Monitoring at the FORCE site is currently focused on lobster, fish, marine mammals, seabirds, and underwater sound and is divided into device-specific (≤ 100 m from a device) and site-level (> 100 m from a device) monitoring. As approved by regulators, individual berth holders are responsible for leading device-specific monitoring in direct vicinity of their devices(s).