Skip to main content

OES-Environmental distributes metadata forms (questionnaires) to solicit information from developers involved in environmental monitoring around marine renewable energy project sites around the world. This page provides project descriptions, baseline assessment, post-installation monitoring, and links to available data and reports. Content is updated on an annual basis.

West Islay Tidal Project Energy Park

Description

The development site lies approximately 6km off the  Rinns of Islay, Islay, Inner Hebrides, Scotland and covers approximately 2 km2 of seabed. The long term goal is to expand the array. In 2009, a two-year marine mammal and bird survey campaign was commenced in the area. Upon the completion of these surveys in 2011, an Agreement for Lease for the development area was granted by the Crown Estate. 

The site development proposals are based on a technology neutral approach to minimise development risk. It is not possible to adopt a completely neutral approach given the physical constraints and resources at the site; therefore a design envelope has been developed based on generic design philosophy. The design envelope includes seabed mounted devices that are either surface piercing or non-surface piercing with horizontal axis turbines. The design envelope considers twin and single horizontal rotor devices up to 20 m diameter. 

Mooring and Foundations:

There are several possible methodologies for securing the turbine in position, these include a gravity base, piled or pin-piled fixed base. The MCT/Siemens device incorporates two turbine units attached to a lifting cross arm mounted on a steel tower anchored in the seabed (the Seagen S). Alstom’s turbine is mounted on a tripod support structure pinned to the seabed. Hammerfest propose a similar tripod foundation but with ballast used to keep the structure in place.4 Alternative floating support structure systems have also been considered as part of the EIA. 
 
Export Cables:

The inter-array cabling will be marshalled and exported to shore via up to three 33kV subsea export cables, landing at Islay. A number of routes and landfall locations  were/ continue to be considered. The preferred option at the time of Marine Consent application and the one which is described within the Environmental Statement (ES) is to route the export cable east from the tidal park to a landfall location at Kintra on Islay. 

Onshore Infrastructure:

The existing infrastructure on Islay will need to be upgraded to facilitate the power transfer from the project to the grid on the mainland which will require deep reinforcement.

Vessel Spread:

The number of vessel movements and type of vessels used will depend on the selected turbine technology.4 This information will be provided in the Construction Method Statement once the final design has been completed; however the installation works is most likely to be carried out by either jack up vessels, dynamic positioning vessels or heavy lift vessels. The vessels that are likely to be used are outline in the following table.

 

Type of installation 
vessel

Option 1:
Large size Jack up barge as installation vessel

Option 2:
Medium size Jack up barge as
installation vessel

Option 3:
Dynamic positioning scenario

Size of vessel

150m x 45m

68m x 38m

155m x 30m

Footprint of mooring system

4 triangular lattice spuds with circa 140m2 spud area

4 circular spuds ca. 10m² spud area
(possibly extended with spud cans)

Dynamic positioning holding a footprint of +/- 5m

No. tugs required

Jack up vessel is typically self-propelled,

Jack up vessel is typically self-propelled, but possible single tug required for initialpositioning (30x22m)

n/a

Anchor handling vessel

n/a

n/a

n/a

Flat top barge (to bring out large items)

n/a

n/a

n/a

Crew change support vessel (vessel length)

Up to 26m

 

Up to 26m

Install vessel

100m x 50m

 

100m x 50m

SeaGen unit installed by

Same vessel

JUP vessel in case SeaGen S unit split up
into multiplesections or by HLV (Heavy
Lifting Vessel)

DP2 vessel in case SeaGen S unit split up into
multiple sections or by HLV
4

 

Location

6 km South West of the Rinns of Islay, Islay, Inner Hebrides, Scotland.

Licensing Information

An application for consent was submitted in 2013. Marine Scotland have consulted on the application and will make recommendations in due course. 

Licence Competent Authority Reference
Marine Licence (Marine (Scotland) Act) Marine Scotland https://marine.gov.scot/data/west-islay-tidal-energy-park-marine-licenc…
Section 36 (Electricity Act) Consent Scottish Ministers TBC
Licence to Disturb Basking Shark Marine Scotland TBC
European Protected Species Licence Marine Scotland TBC

Project Progress

In October 2011 The Crown Estate granted an Agreement for Lease. A suite of environmental baseline characterization surveys to inform EIA commenced in 2011.  The Environmental Statement was published in 2013 in support of an application for statutory consents. The project was co-developed from 2014 to 2019 by DP Energy and Bluepower through SPV West Islay Tidal Energy Park Ltd. (WITEP). From 2020, WITEP was 100% owned by Bluepower.

This WITEP project no longer has an active lease site within Scotland.

Key Environmental Issues

Several potential impacts were identified during the Environmental Impact Assessment, however only the following were deemed to be potentially significant:

  • Mortality or death of marine mammals as a result of collisions with operating turbines; and
  • Temporary loss of fishing grounds due to the construction of the development.

The below baseline assessments were undertaken (or commissioned by) the developer to inform baseline characterisation.

The mitigation and monitoring measures in the Post-Installation Monitoring table are proposed within the project ES. The project team, along with Marine Scotland and other key stakeholders are currently preparing a Preliminary Environmental Monitoring Plan (PEMP) which will outline the proposed monitoring strategy in more detail.
 

Mitigation measures:
A number of key mitigation and best practice measures have been proposed throughout the ES. These are as follows:

  • Development of an Environmental Management Plan (EMaP) to be agreed with SNH and Marine Scotland, following submission of this ES. The EMaP will be a working document detailing the environmental actions highlighted in the ES, all activities to be carried out on site, responsibilities for those activities, environmental risks and the management protocols to be put in place to control these, as well as identification of personnel responsible for each element of the EMaP;
  • An Environmental Monitoring Programme (EMP), to be agreed with Marine Scotland (MS) and Scottish Natural Heritage (SNH);
  • A detailed Construction Method Statement (CMS) and a Pollution Control and Spillage Response Plan to be prepared and agreed with SEPA, SNH and MS-LOT prior to commencement of construction;
  • All work will be undertaken to an overarching Health, Safety and Environmental Management System (HSEMS), which will include the CMS, the PIRP and the EMaP. The project will be supervised in accordance with the Construction Design and Management Regulations (2007); and
  • Pollution Control and Spillage Response Plans to be developed and included in the EMaP.